Project Management Quiz Cost

Project Management Quiz Cost

Professional Development

23 Qs

quiz-placeholder

Similar activities

Machine Availability & Reliability

Machine Availability & Reliability

Professional Development

20 Qs

B2 high Quiz (Units 13-14)

B2 high Quiz (Units 13-14)

Professional Development

20 Qs

Plan O

Plan O

Professional Development

20 Qs

PROFESSIONAL PRACTICE

PROFESSIONAL PRACTICE

Professional Development

20 Qs

Budget Call and Budget Preparation Phase Questions

Budget Call and Budget Preparation Phase Questions

Professional Development

20 Qs

Project Management Quiz - Schedule

Project Management Quiz - Schedule

Professional Development

23 Qs

Basic Administrative Finance Project Information

Basic Administrative Finance Project Information

KG - Professional Development

22 Qs

Budgeting - Level 2

Budgeting - Level 2

Professional Development

20 Qs

Project Management Quiz Cost

Project Management Quiz Cost

Assessment

Quiz

Other

Professional Development

Hard

Created by

Citizen TV

FREE Resource

23 questions

Show all answers

1.

OPEN ENDED QUESTION

1 min • 1 pt

What does the SPI tell you if 40% of the project is completed after four months and the actual cost is $25,000?

Evaluate responses using AI:

OFF

2.

OPEN ENDED QUESTION

1 min • 1 pt

What does the CPI tell you if 40% of the project is completed and the actual cost is $30,000?

Evaluate responses using AI:

OFF

3.

OPEN ENDED QUESTION

1 min • 1 pt

What would you call an estimate with a range of $75,000 to $200,000 and the actual cost around $150,000?

Evaluate responses using AI:

OFF

4.

OPEN ENDED QUESTION

1 min • 1 pt

What is the SPI if the first five components of a project are completed at a cost of $8,000 out of fifteen components?

Evaluate responses using AI:

OFF

5.

OPEN ENDED QUESTION

1 min • 1 pt

What will you do FIRST upon discovering significant cost overruns due to damages in the foundation of a project?

Evaluate responses using AI:

OFF

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Steve, a project manager, is trying to figure out the performance that must be achieved in order to meet the financial and schedule goals in his project. He is using a measurement that will give him the status on the remaining work with respect to the funds remaining. Which of the following measures is Steve using?

Cost aggregation

Variance analysis

Trend analysis

To-Complete Performance Index (TCPI)

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager working on a construction project planned to install new carpets in all four rooms of the house. She measured the square footage of all the rooms and then multiplied that figure by a set cost factor to estimate the cost for installing the carpet. This is an example of:

Bottom-up estimating

Analogous estimating

Parametric estimating

Three-point estimating

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?