Cost (Chapter 7)

Quiz
•
Life Project
•
Professional Development
•
Hard

Asma Budi Aswadi
Used 3+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager has recently been given a promotion and become the sponsor of a new initiative within her company. Given her past success in managing similar projects, the organization’s project steering committee asks her to submit a high-level project estimate that will be reviewed next week to decide on whether or not to initiate the project.
What is the best course of action for the new sponsor?
Get a professional estimate from external subject matter experts
Use her own expert judgment and some historical information
Use the WBS to create an accurate bottom-up estimate
Work with the project team to create the requested estimate
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A senior executive suggests initiating a project to replace a significant portion of the company’s labor force with an automated production line. Other company executives are skeptical that this approach is the best way to increase profit margins and wonder if they are ready to sponsor such an effort.
What is the best first thing that should be done in this scenario?
Performing a needs assessment
Consulting with the project management office
Appointing a project sponsor to create a project charter
Providing a project manager with the authority to apply organizational resources
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A team of efficiency experts hired by your company has concluded that the transportation costs associated with your project are excessive. You have been requested by the sponsor to cut the costs.
What should be done next?
Perform a root cause analysis
Conduct a cost reduction analysis
Carry out a trend analysis
Use a decision tree analysis
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project initiation, the project manager had provided an initial estimate of $250.000 with a range of -25% to +75%. The project is now in planning, and, as part of the Estimate Costs process, the project manager has to refine the estimate a much narrower range.
How should the project manager determine the estimating methods that can be used and the accuracy required for the cost estimate?
Review the cost management plan
Examine the basis of estimate
Contact the finance department
Check the project charter
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
On a project, several programmers were hired as independent contractors to supplement the in-house programmers to ensure the timely completion of the project. Toward the end of the project, the project manager performed some analysis and determined that CPI was 0.8 and the SPI was 1.2.
What is the best course of action to bring project performance back into alignment with the project management plan?
Approve the use of overtime for the in-house programmers
Reduce or eliminate the independent contractors
Perform fast tracking to address the performance gap
Eliminate the non-essential features from the project scope
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
As part of monitoring and controlling costs for your project, you need to calculate a cost variance (CV). You have already determined that $22,000 has been spent thus far on the project.
In order to calculate the CV, what should you do next?
Check the project cost management plan
Examine the quality control measurements
Look up the budget at completion for the project
Review the cost baseline and the project schedule
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics.
At the retrospective, the team determine that the costs performance index (CPI) of the iteration was ………………
1.333
0.750
1.143
0.857
Create a free account and access millions of resources
Similar Resources on Wayground
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade
Discover more resources for Life Project
11 questions
All about me

Quiz
•
Professional Development
10 questions
How to Email your Teacher

Quiz
•
Professional Development
15 questions
Fun Random Trivia

Quiz
•
Professional Development
22 questions
Anne Bradstreet 1612-1672

Quiz
•
Professional Development
18 questions
Spanish Speaking Countries and Capitals

Quiz
•
KG - Professional Dev...
14 questions
Fall Trivia

Quiz
•
11th Grade - Professi...
15 questions
Disney Characters Quiz

Quiz
•
Professional Development
15 questions
Quiz to Highlight Q types & other great features in Wayground

Quiz
•
Professional Development