Which of the following is a false statement about the WBS?

A control account may have many code of account identifiers.

You should keep decomposing WBS components to lower levels until necessary and sufficient decomposition has been achieved.

Each work component appears in the WBS once and only once.

The work packages should appear from left to right in the order in which the work will be performed.

Answer explanation

Answer: D is the correct answer, because the work packages do not have to appear in the order in which the

work is performed. That order will be determined later.

A, B, and C are incorrect answers because these are the characteristics of the WBS.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is done first?

Creating the scope statement

Creating the WBS

Creating the requirement documentation

Creating the project charter

Answer explanation

Answer: D is correct, because the project charter is created in the initiation phase and serves as input for the creation of the requirements documentation and the scope statement.

A is incorrect because the project charter is an input item to creating the project scope statement.

B is incorrect because the project scope statement is an input item to creating the WBS.

C is incorrect because the project charter is an input to creating the requirements documentation.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The WBS is the output of which of the following processes?

Create WBS process

Define Scope process

Develop WBS process

Project Initiating process

Answer explanation

Answer: A is correct because the Create WBS process is used to create the WBS.

B and C are incorrect because there are no standard processes named Project Work process or Develop WBS.

D is incorrect because project initiating is a process group that includes two processes: one to develop the project

charter and one to identify stakeholders.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project scope statement is the output of which of the following processes?

Create WBS process

Define Scope process

Create Project Scope process

Project Initiating process

Answer explanation

Answer: B is correct because the Define Scope process is used to create the project scope statement.

A is incorrect because the Create WBS process is used to create the WBS.

C is incorrect because there is no such standard process named Create Project Scope.

D is incorrect because project initiating is a process group that includes two processes: one to develop the project charter and one to identify stakeholders.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a false statement about the output of the Plan Scope Management process that creates the project scope management plan?

It describes how to verify the project scope.

It describes how to control the project scope.

It doesn’t describe how to manage the requirements.

It describes how to define the product scope.

Answer explanation

Answer: C is the correct answer because the Plan Scope Management process also generates the requirement

management plan.

A, B, and D are incorrect because all these are true statements about the project scope management plan, the

other output of the Plan Scope Management process.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the components in the lowest level of the WBS hierarchy collectively called?

Work packages

Control accounts

Phase

Milestones

Answer explanation

Answer: A is correct because the components in the lowest level of the WBS hierarchy are called work packages.

B is incorrect because a control account might consist of more than one work package.

C is incorrect because if a phase is represented in the WBS, it will be represented at a much higher level.

D is incorrect because a milestone might consist of more than one work package.

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Choose what is included in the project scope statement:

(multiple answers)

Project scope

Product scope

Assumptions and constraints

Some things that the project is not going to do

Answer explanation

Answer: A, B, C, D are correct because all of these are included in the project scope statement.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?