PMP Exam Prep 2024 - Chapter 3 - Project Scope Management
Authored by Patrick Pepin
Professional Development
Professional Development
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a false statement about the WBS?
A control account may have many code of account identifiers.
You should keep decomposing WBS components to lower levels until necessary and sufficient decomposition has been achieved.
Each work component appears in the WBS once and only once.
The work packages should appear from left to right in the order in which the work will be performed.
Answer explanation
Answer: D is the correct answer, because the work packages do not have to appear in the order in which the
work is performed. That order will be determined later.
A, B, and C are incorrect answers because these are the characteristics of the WBS.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is done first?
Creating the scope statement
Creating the WBS
Creating the requirement documentation
Creating the project charter
Answer explanation
Answer: D is correct, because the project charter is created in the initiation phase and serves as input for the creation of the requirements documentation and the scope statement.
A is incorrect because the project charter is an input item to creating the project scope statement.
B is incorrect because the project scope statement is an input item to creating the WBS.
C is incorrect because the project charter is an input to creating the requirements documentation.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The WBS is the output of which of the following processes?
Create WBS process
Define Scope process
Develop WBS process
Project Initiating process
Answer explanation
Answer: A is correct because the Create WBS process is used to create the WBS.
B and C are incorrect because there are no standard processes named Project Work process or Develop WBS.
D is incorrect because project initiating is a process group that includes two processes: one to develop the project
charter and one to identify stakeholders.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project scope statement is the output of which of the following processes?
Create WBS process
Define Scope process
Create Project Scope process
Project Initiating process
Answer explanation
Answer: B is correct because the Define Scope process is used to create the project scope statement.
A is incorrect because the Create WBS process is used to create the WBS.
C is incorrect because there is no such standard process named Create Project Scope.
D is incorrect because project initiating is a process group that includes two processes: one to develop the project charter and one to identify stakeholders.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a false statement about the output of the Plan Scope Management process that creates the project scope management plan?
It describes how to verify the project scope.
It describes how to control the project scope.
It doesn’t describe how to manage the requirements.
It describes how to define the product scope.
Answer explanation
Answer: C is the correct answer because the Plan Scope Management process also generates the requirement
management plan.
A, B, and D are incorrect because all these are true statements about the project scope management plan, the
other output of the Plan Scope Management process.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are the components in the lowest level of the WBS hierarchy collectively called?
Work packages
Control accounts
Phase
Milestones
Answer explanation
Answer: A is correct because the components in the lowest level of the WBS hierarchy are called work packages.
B is incorrect because a control account might consist of more than one work package.
C is incorrect because if a phase is represented in the WBS, it will be represented at a much higher level.
D is incorrect because a milestone might consist of more than one work package.
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Choose what is included in the project scope statement:
(multiple answers)
Project scope
Product scope
Assumptions and constraints
Some things that the project is not going to do
Answer explanation
Answer: A, B, C, D are correct because all of these are included in the project scope statement.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
29 questions
Alg. 1 Section 5.1 Coordinate Plane
Quiz
•
9th Grade
22 questions
fractions