PMP Exam Prep 2024 - Chapter 3 - Project Scope Management

Quiz
•
Professional Development
•
Professional Development
•
Hard

Patrick Pepin
Used 3+ times
FREE Resource
Student preview

15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a false statement about the WBS?
A control account may have many code of account identifiers.
You should keep decomposing WBS components to lower levels until necessary and sufficient decomposition has been achieved.
Each work component appears in the WBS once and only once.
The work packages should appear from left to right in the order in which the work will be performed.
Answer explanation
Answer: D is the correct answer, because the work packages do not have to appear in the order in which the
work is performed. That order will be determined later.
A, B, and C are incorrect answers because these are the characteristics of the WBS.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is done first?
Creating the scope statement
Creating the WBS
Creating the requirement documentation
Creating the project charter
Answer explanation
Answer: D is correct, because the project charter is created in the initiation phase and serves as input for the creation of the requirements documentation and the scope statement.
A is incorrect because the project charter is an input item to creating the project scope statement.
B is incorrect because the project scope statement is an input item to creating the WBS.
C is incorrect because the project charter is an input to creating the requirements documentation.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The WBS is the output of which of the following processes?
Create WBS process
Define Scope process
Develop WBS process
Project Initiating process
Answer explanation
Answer: A is correct because the Create WBS process is used to create the WBS.
B and C are incorrect because there are no standard processes named Project Work process or Develop WBS.
D is incorrect because project initiating is a process group that includes two processes: one to develop the project
charter and one to identify stakeholders.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project scope statement is the output of which of the following processes?
Create WBS process
Define Scope process
Create Project Scope process
Project Initiating process
Answer explanation
Answer: B is correct because the Define Scope process is used to create the project scope statement.
A is incorrect because the Create WBS process is used to create the WBS.
C is incorrect because there is no such standard process named Create Project Scope.
D is incorrect because project initiating is a process group that includes two processes: one to develop the project charter and one to identify stakeholders.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a false statement about the output of the Plan Scope Management process that creates the project scope management plan?
It describes how to verify the project scope.
It describes how to control the project scope.
It doesn’t describe how to manage the requirements.
It describes how to define the product scope.
Answer explanation
Answer: C is the correct answer because the Plan Scope Management process also generates the requirement
management plan.
A, B, and D are incorrect because all these are true statements about the project scope management plan, the
other output of the Plan Scope Management process.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are the components in the lowest level of the WBS hierarchy collectively called?
Work packages
Control accounts
Phase
Milestones
Answer explanation
Answer: A is correct because the components in the lowest level of the WBS hierarchy are called work packages.
B is incorrect because a control account might consist of more than one work package.
C is incorrect because if a phase is represented in the WBS, it will be represented at a much higher level.
D is incorrect because a milestone might consist of more than one work package.
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Choose what is included in the project scope statement:
(multiple answers)
Project scope
Product scope
Assumptions and constraints
Some things that the project is not going to do
Answer explanation
Answer: A, B, C, D are correct because all of these are included in the project scope statement.
Create a free account and access millions of resources
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
10 questions
Afterschool Activities & Sports

Quiz
•
6th - 8th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
15 questions
Cool Tool:Chromebook

Quiz
•
6th - 8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
20 questions
Bullying

Quiz
•
7th Grade
18 questions
7SS - 30a - Budgeting

Quiz
•
6th - 8th Grade
Discover more resources for Professional Development
11 questions
All about me

Quiz
•
Professional Development
10 questions
How to Email your Teacher

Quiz
•
Professional Development
5 questions
Setting goals for the year

Quiz
•
Professional Development
8 questions
Ötzi the Iceman: A 5,000-Year-Old True Crime Murder Mystery | Full Documentary | NOVA | PBS

Interactive video
•
Professional Development