3.3 Quiz
Authored by Briana Talley
others
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
17 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
30 sec • 10 pts
KANBAN PRACTICE: Label the tasks below to into the correct To Do, In Progress, or Complete column. Amanda needs to secure catering and prepare for the annual shareholders meeting on the 15th. Each Shareholder will receive refreshments and an agenda on arrival. Votes will be cast with a voting drop box.
Amanda has:
- already emailed shareholders,
- not created the voting cards,
- purchased proxy cards,
- started but not assembled the agenda booklets
- contacted a caterer and they are negotiating a contract, and
- not ordered attendee badges.
* (1) and (4) *
2.
MULTIPLE SELECT QUESTION
30 sec • 10 pts
KANBAN PRACTICE: Label the tasks below to into the correct To Do, In Progress, or Complete column. Amanda needs to secure catering and prepare for the annual shareholders meeting on the 15th. Each Shareholder will receive refreshments and an agenda on arrival. Votes will be cast with a voting drop box.
Amanda has:
- already emailed shareholders,
- not created the voting cards,
- purchased proxy cards,
- started but not assembled the agenda booklets
- contacted a caterer and they are negotiating a contract, and
- not ordered attendee badges.
* (2) and (5) *
3.
MULTIPLE SELECT QUESTION
30 sec • 10 pts
KANBAN PRACTICE: Label the tasks below to into the correct To Do, In Progress, or Complete column. Amanda needs to secure catering and prepare for the annual shareholders meeting on the 15th. Each Shareholder will receive refreshments and an agenda on arrival. Votes will be cast with a voting drop box.
Amanda has:
- already emailed shareholders,
- not created the voting cards,
- purchased proxy cards,
- started but not assembled the agenda booklets
- contacted a caterer and they are negotiating a contract, and
- not ordered attendee badges.
* (3) and (6) *
4.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
A visual management method known as __________ tracks projects through a flow system and is where work is organized.
5.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
To further organize information, adding __________ to a Kanban board adds a horizontal separation that can be used to further organize information for each team group or component of a project.
6.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
The __________ is responsible for flow in the downstream board, and helps maintain a team's focus.
7.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
What do you call the process of diagrams that record daily values and progress, and displays the information on one chart?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?