PMI SH Plan and Manage Scope

PMI SH Plan and Manage Scope

1st Grade

10 Qs

quiz-placeholder

Similar activities

OPM_2

OPM_2

1st Grade

10 Qs

Bi Weekly DMAIC - DEFINE

Bi Weekly DMAIC - DEFINE

1st - 10th Grade

10 Qs

04. Integration Management

04. Integration Management

1st Grade

12 Qs

Chapt3

Chapt3

1st Grade

10 Qs

09. Resource Management

09. Resource Management

1st - 3rd Grade

12 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

CARMA

CARMA

1st - 8th Grade

10 Qs

PMP 2017 PEOPLE

PMP 2017 PEOPLE

1st - 12th Grade

10 Qs

PMI SH Plan and Manage Scope

PMI SH Plan and Manage Scope

Assessment

Quiz

Professional Development

1st Grade

Medium

Created by

sudiyuwono wowo

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

During acceptance testing of a deliverable, some senior stakeholders complain that a feature essential to their department was not included. What should the project manager have done to prevent this?

Consulted lessons learned from similar projects to adapt processes

Prepared a change management plan and logged changes during project implementation

Analyzed the project charter and developed a scope management plan

Prepared a prototype and conducted a product demo with stakeholders

Answer explanation

Analyzed the project charter and developed a scope management plan is correct, because the question is about what Project Manager should have done to prevent this situation. The scope management plan is a component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified.

The remaining options are not correct for the reasons explained below

  • Consulted ... appears to be close but it is a distractor because lessons learned provides an insight of how other projects were executed in general

  • Prepared a change.... is the next step but not what should have been done to prevent this situation

  • Prepared a Prototype.... is on the basis of Scope and Requirements which is part of Scope Management plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is involved in a project where requirements are constantly evolving.

What should the project manager do to achieve success?

Provide regular updates and request deliverable-based approvals from the product owner.

Work with the team to ensure they are on track and delivering on schedule.

Maintain a comfortable working atmosphere to improve team cohesion.

Ensure documentation and processes are filed appropriately and update the product owner.

Answer explanation

The project manager is dealing with a project with an evolving scope. Such projects require the project manager to engage constantly with the product owner for feedback and sign off on project deliverables.

The other answer choices are incorrect. They are all proper PM processes, however they don't focus on the evolving scope in the question.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

A new product was accepted by the customer, but after two weeks the project manager received a complaint from the customer saying that the product's functionality requirements were not met.

What should the project manager do first?

Escalate the issue to the project sponsor.

Review the scope validation process.

Schedule an inspection of the product.

Validate the scope with the customer.

Answer explanation

The scope validation process is intended to confirm that a product meets the needs of the customer and other identified stakeholders. The customer reviews the criteria required to be met before they accept the deliverable. If the customer is complaining that the product functionality requirements were not met, it suggests that there are issues with the scope validation process. The project manager should review the scope validation process to identify the root cause of the discrepancy and ways to address it.
The other options are incorrect.
Validating the scope with the customer occurs before they accept the product, so it should have been done already.
Inspecting the production may be necessary in the future, but it is too early to determine if it is needed. 
Escalating the issue to the project sponsor should only be done after the project manager determines the root cause of the problem. 

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

A project team completes the identification of project and product requirements. Which of the following were used to accomplish this?

Benchmarking, network diagram, and trend analysis

Work breakdown structure (WBS), trend analysis, and observation/conversation

Brainstorming, affinity diagrams, and mind mapping

Affinity diagrams, benchmarking, and observation/conversation

Answer explanation

PMBoK Sixth Edition Chapter 4 states: "EXECUTING PROCESS GROUP

The Executing Process Group consists of those processes performed to complete the work defined in the project management plan to satisfy the project requirements. This Process Group involves coordinating resources, managing stakeholder engagement, and integrating and performing the activities of the project in accordance with the project management plan. The key benefit of this Process Group is that the work needed to meet the project requirements and objectives is performed according to plan. A large portion of the project budget, resources, and time is expended in performing the Executing Process Group processes. The processes in the Executing Process Group may generate change requests. If approved, the change requests may trigger one or more planning processes that result in a modified management plan, project documents, and possibly new baselines. The Executing Process Group includes the project management processes identified

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

A project team discovers an opportunity to enhance software without impacting the budget or schedule. The team makes the enhancement without proper documentation, which later causes production issues.

What process should have been conducted to prevent this?

Control Schedule

Perform Qualitative Risk Analysis

Plan Scope Management

Perform Integrated Change Control

Answer explanation

As per PMBoK Sixth Edition Chapter 5 states: "

The Monitoring and Controlling Process Group consists of those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes. Monitoring is collecting project performance data, producing performance measures, and reporting and disseminating performance information. Controlling is comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed. The key benefit of this Process Group is that project performance is measured and analyzed at regular intervals, appropriate events, or when exception conditions occur in order to identify and correct variances from the project management plan. The Monitoring and Controlling Process Group also involves:

Evaluating change requests and deciding on the appropriate response;

Recommending corrective or preventive action in anticipation of possible problems;

Monitoring the ongoing project activities against the project management plan and project baselines; and

Influencing the factors that could circumvent the change control process so only approved changes are implemented.

Continuous monitoring provides the project team and other stakeholders with insight into the status of the project and identifies any areas that require additional attention. The Monitoring and Controlling Process Group monitors and controls the work being done within each Knowledge Area, each Process Group, each life cycle phase, and the project as a whole. The Monitoring and Controlling Process Group includes the project management processes identified in Sections 5.1 through 5.12"

The Project Team cannot make "Changes - Enhancements or otherwise" with performing Integrated Change Control. Documentation is a must.

The "Distractors" are correct as they not relevant but are able to distract for the correct answer "Perform Integrated Change Control"

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a new software development project and has met with the customer to discuss their requirements. The customer has provided the project manager with a list of requirements, but did not differentiate the technical requirements from the customer requirements.

Which of the following requirements should the project manager classify as a customer requirement?

The software should be able to process 1000 transactions per second.

The software should use a secure database encryption algorithm.

The software should be able to run on a variety of operating systems.

The software should be easy to use and navigate.

Answer explanation

Customer requirements refer to the specifications or features of a product or service deemed necessary by customers that must be completed (developed and tested) for the project to be completed. They are more general and describe what the customer wants the product or service to do. They are typically expressed in the customer's own words and may not be specific enough to be implemented and tested. It is important to note that customer requirements are the starting point for technical requirements. The project team needs to work with the customer to understand their requirements and then translate those requirements into more specific technical requirements that can be implemented.

The other answer choices are incorrect because they are classified as technical requirements. They are specific enough to be implemented and tested. They describe what the software should do, how it should behave, and the desired quality attributes it should have.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The sponsor of a hybrid project wants to see a more detailed breakdown in the project charter, not just the milestones. The project manager informs the sponsor that preparing the breakdown will require two more iterations.

Why is this additional time required?

The milestone schedule was prepared based on the project manager's experience only.

The steering committee has to review and approve the schedule first.

Scope in the charter should be approved before detail planning with the team can occur.

Schedule details are only planned one iteration in advance in a hybrid approach.

Answer explanation

Project Charter scope needs to be agreed on by the sponsor before the team starts detailed planning.

The other answer choices are incorrect because they are not relevant as the ask is about detail planning and not on a milestone schedule.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?