Inspection and Test Revision Paper 2A

Inspection and Test Revision Paper 2A

Professional Development

30 Qs

quiz-placeholder

Similar activities

Examen Técnico REBT ITC 1 A 24

Examen Técnico REBT ITC 1 A 24

Professional Development

31 Qs

Medical Gas Systems 2021 101-125

Medical Gas Systems 2021 101-125

Professional Development

25 Qs

ESTIMER MON NIVEAU WORDPRESS : LE GRAND QUIZ

ESTIMER MON NIVEAU WORDPRESS : LE GRAND QUIZ

Professional Development

31 Qs

HVAC State Test Prep 06

HVAC State Test Prep 06

Professional Development

30 Qs

ICIT: Revision (Fire Alarm)

ICIT: Revision (Fire Alarm)

Professional Development

30 Qs

OVH GENERATOR

OVH GENERATOR

Professional Development

25 Qs

2018 IFGC CH 5A

2018 IFGC CH 5A

Professional Development

25 Qs

Comm Nav Q2

Comm Nav Q2

Professional Development

30 Qs

Inspection and Test Revision Paper 2A

Inspection and Test Revision Paper 2A

Assessment

Quiz

Other

Professional Development

Hard

Created by

Amir Karbassi

Used 2+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

On completion of a new installation, the interval before the first periodic inspection would be decided by:

installer

installation designer

client

inspection and testing engineer.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Any addition to an existing installation should:

have a similar wiring system to that used in the existing installation

be inspected and tested separate from the existing installation

not impair the safety of the existing installation

have its own energy meter separate from that of the existing installation.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following duties is 'not' the responsibility of the inspector:

to carry out maintenance and repairs on the installation

to compare the test results with the design criteria

to advise on remedial works

to recommend the immediate isolation of defective parts.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Inspection of a fully enclosed domestic consumer unit would not need verification for:

identification of conductors

rating and type of protective devices

IP rating

correct connection of single-pole devices.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When inspecting for adequate 'basic protection' (protection against electric shock or direct contact) which of the following does not require inspection. Presence and condition of:

insulation

enclosures

barriers

cpc's.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The measured value of loop impedance for a circuit is 2.4Ω. If the temperature at the time of the test was 20°C and the cable is 70°C (factor 1.2) what is the corrected value. Ze = 0.4Ω:

2.88 Ω

2.8 Ω

2.4 Ω

2.0 Ω.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Put the following tests in the correct sequence: 1- earth fault loop impedance 2- polarity 3- ring circuit continuity 4- prospective fault current:

1,3,2,4

2,4,1,3

1,4,3,2

4,1,2,3

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?