pm_5

pm_5

University

27 Qs

quiz-placeholder

Similar activities

CURRICULUM EVALUATION

CURRICULUM EVALUATION

University

22 Qs

SE4 - Software Configuration and Control

SE4 - Software Configuration and Control

University

26 Qs

INS200 - QUIZ 1 (MAR-JULY 2020)

INS200 - QUIZ 1 (MAR-JULY 2020)

University

25 Qs

專案管理ch7

專案管理ch7

University

31 Qs

Weekly Quiz 15

Weekly Quiz 15

University

23 Qs

Chapter 9 - Module 7

Chapter 9 - Module 7

University

30 Qs

Chapter 5: Digital and Social Media Marketing

Chapter 5: Digital and Social Media Marketing

University - Professional Development

23 Qs

Project Risk Management

Project Risk Management

University

30 Qs

pm_5

pm_5

Assessment

Quiz

Education

University

Medium

Created by

Nurzhan Zeinolla

Used 6+ times

FREE Resource

27 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Paul plans to use a systematic forecasting method to gather the opinions of a panel of experts on a problem the team is encountering. Which method will Paul employ?

Root cause analysis

Interviewing

Brainstorming

Delphi technique

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The team is reviewing the overall project risk monitoring process and the effectiveness of risk response strategies so that the team can make adjustments for the remainder of the project. What action is the team taking?

Contingency reserve review

Risk reassessment

Risk audit

Quality audit

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

A team is reviewing risk responses. One response states that the project manager will contract an external Subject Matter Expert (SME) if internal skill sets are insufficient. The team recognizes that this response may lead to a risk of potential issues in selecting a vendor and schedule delays. What two types of risk are identified in this scenario?

Threats

Secondary risk

Residual risk

Opportunity

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A team initiates a risk response to install all electrical equipment in a facility. There is a risk of documenting negative impact if the permit process runs long. They implement a response to pay an expedited fee to receive the permits on time. The permits arrive, but the team does not authorize part of the work to be accomplished. A new risk is added to the risk register. How is this risk classified?

Risk audit finding

Secondary risk

Residual risk

Risk defect

5.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

A recently completed risk audit discloses several new risks resulting from implementing a risk response. The response attempts to mitigate a legal condition that led to potential fines. The response needs to be revised. Some fines are prevented, but other fines are incurred. The project manager documents a new risk because of this response failure. The team determines that the updated response could lead to new legal ramifications if executed. What two ways would you categorize these new risks?

Secondary

Watch

Urgent

Residual

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager conducts frequent brainstorming sessions to gather marketing information on new product offerings. Stakeholders complain that they need more time to prepare for these sessions and request an overview of what the team would brainstorm a few days before each meeting. Which technique would satisfy this need?

Brain writing

Root cause analysis

Lessons learned

Interviews

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which two statements are true regarding the need to perform periodic risk reassessments?

All risks are known after risk planning

Risk owners may discover new risks or current risk updates

The project manager finalizes risk scores at the beginning of the project

The risk monitoring process may require updates

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?