PMI SH - Negotiate Project Agreements

PMI SH - Negotiate Project Agreements

1st Grade

16 Qs

quiz-placeholder

Similar activities

03. Chapter123_PM  Framework

03. Chapter123_PM Framework

1st Grade

12 Qs

Pre-Test CAPM

Pre-Test CAPM

1st Grade

16 Qs

04. Integration Management

04. Integration Management

1st Grade

12 Qs

08. Quality Management

08. Quality Management

1st - 3rd Grade

12 Qs

PMI SH Manage Project Issues

PMI SH Manage Project Issues

1st Grade

12 Qs

PMI SH - Integrate Project Planning Activities

PMI SH - Integrate Project Planning Activities

1st Grade

18 Qs

PMI SH Plan and Manage Budget and Resources

PMI SH Plan and Manage Budget and Resources

1st Grade

14 Qs

RMP - 2. STRATEGY & PLANNING

RMP - 2. STRATEGY & PLANNING

1st Grade

16 Qs

PMI SH - Negotiate Project Agreements

PMI SH - Negotiate Project Agreements

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

sudiyuwono wowo

FREE Resource

16 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a complex project with many stakeholders and conflicting priorities. Senior management asked the project manager to avoid "noise" specifically for political projects.

Although it is difficult to find resources for the project, what should the project manager do to ensure smooth progress of the project?

Apply "If you do something nice for me I'll do something nice for you."

Be consistent with words and actions to avoid conflicts with the stakeholders.

Utilize compliments to obtain resources, and cooperate toward mutual goals.

Allocate the scarce resources efficiently to meet the needs of the project.

Answer explanation

Solution: D. Allocate the scarce resources efficiently to meet the needs of the project.

In projects, constraints are time, money, and resources. Resources are considered to be the top criteria for conflict management. Allocating the scarce resources to meet the project needs should be the top priority for the Project Manager. Hence this option is the correct answer.

Negotiation with stakeholders are always performed in the interest of the project and not on personal goals or ambitions. Hence all the remaining options are incorrect.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a complex project with many stakeholders that have conflicting priorities. Senior management asked the project manager to avoid "noise" because this is a highly political project. The project manager opted to use expert opinion from well known industry profiles.

What did the project manager do to satisfy senior management's request?

Responded in a friendly manner to senior management

Appeared to be consistent in the use of words and actions

Cooperated with senior management to achieve mutual goals

Took action based on the senior management's power to act

Answer explanation

Solution: D. Took action based on the senior management's power to act

Use the Law of Authority to establish your own credentials or credibility early in the negotiation process. When establishing your approach or explaining how or why decisions have been made, link your position to known, respected sources in order to garner credibility.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on an complex project with multiple stakeholders and competing priorities. Each stakeholder wants to maximize its share of the allocated resources for the requested functionality.

What should the project manager focus on?

Meeting the personal interests of stakeholders.

Meeting the mutual interests of all stakeholders.

Preserving the relationships and rapport with stakeholders.

Pushing stakeholders to accept the project manager's viewpoint.

Answer explanation

Solution: B. Meeting the mutual interests of all stakeholders.

The project manager should focus on finding a solution that meets the needs of all stakeholders, even if it means making some compromises. This will help ensure the project's success and maintain good relationships with stakeholders.

The other answer choices are incorrect. Meeting the personal interests of stakeholders is not always possible, and it may not be in the project's best interests. Preserving the relationships and rapport with stakeholders is important but not the most important thing. The project manager should focus on meeting the needs of stakeholders, even if it means some relationships are impacted. Pushing stakeholders to accept the project manager's viewpoint is not a good strategy. This will only alienate stakeholders and make it more difficult to reach a consensus.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A complex project, involving multiple stakeholders with diverse priorities, requires long and challenging negotiations to finalize the project agreement. The project manager must facilitate setting the right priorities for these crucial negotiations.

What should the project manager do first?

Develop a detailed risk register

Organize a brainstorming session with all stakeholders.

Define clear project success criteria.

Conduct individual interviews with key stakeholders. 

Answer explanation

Solution: C. Define clear project success criteria.

By prioritizing the definition of clear success criteria, the project manager sets a strong foundation for effective negotiations. This ensures all parties are focused on achieving the project's desired outcomes and facilitates aligning stakeholder priorities with those goals.

The other answer choices are incorrect as they should be done after clear project success criteria have been defined. While risk management is crucial, prioritizing all risks does not address specific stakeholder priorities and their bargaining points. Stakeholder brainstorming sessions can be valuable later in the process, but at the initial stage, focusing on success criteria provides a clearer direction for stakeholder engagement. Individual stakeholder interviews can offer valuable insights, but prioritizing defining success criteria first offers a broader framework for conducting interviews and understanding priorities in context.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a complex, political project with many stakeholders having conflicting priorities. Senior management asked the project manager to ensure that there was no "noise" regarding the project. During a stakeholder meeting, the project manager asked a series of questions to confirm acceptance for each deliverable before asking for acceptance of the whole project.

What did the project manager do to satisfy stakeholders?

Responded to positive actions of the stakeholders to reward actions

Acted in a manner that was consistent in the use of words and actions

Engaged with stakeholders by cooperating toward mutual goals

Acted based on the power authorized by senior management

Answer explanation

Solution: B. Acted in a manner that was consistent in the use of words and actions

Law of Commitment and Consistency can be called “Get the other person saying ‘yes, yes’ immediately.” This occurs when one party asks the other side to make a number of “small” decisions that lead to only one obvious conclusion: to accept the general concession.

The approved project charter formally initiates the project.

A project charter may still be used to establish internal agreements within an organization to ensure proper delivery under the contract.

The Project Manager has to negotiate project agreements. Project Manager has to persuade the Stakeholders and achieve acceptance.

The correct answer is: "Acted in a manner that was consistent in the use of words and actions"

The Distractors are accepted

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A company is working on a hybrid project in which the deliverables have quality issues at the end of one of the sprints. Which action should the project manager take?

Review the definition of done (DoD).

Look for a clear set of working agreements.

Apply value stream mapping.

Use a plan-driven approach.

Answer explanation

Solution: A. Review the definition of done (DoD).

The definition of done (DoD) is a set of criteria that must be met before a deliverable is considered complete. By reviewing the DoD, the project manager can identify the specific quality issues that need to be addressed and develop a plan to fix them. This will help to ensure that the deliverables meet the project's quality standards.

The other answer choices are not as relevant or effective. Working agreements are important for setting expectations and managing conflict, but they are not directly related to addressing quality issues. Value stream mapping is a tool for identifying and eliminating waste in a process. It is not specifically designed to address quality issues. A plan-driven approach is a project management methodology that emphasizes planning and control. It is not as flexible as a hybrid approach, which may be needed to address quality issues.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Halfway through a year-long project, a hardware supplier sends a project manager notice of an intent to increase prices due to fluctuating rates of exchange. The project manager is unsure of their negotiating authority.

Which document should the project manager reference?

Risk register

Procurement management plan

Project Charter

Communication strategy

Answer explanation

Solution: B. Procurement management plan

The procurement management plan is a component of the project or program management plan that describes how a project team will acquire goods and services from outside of the performing organization. In most organizations, project managers do not have contracting authority. Rather, they work with contracting officers or other people with expertise in contracts, laws, and regulations. Organizations usually have rigorous policies and procedures associated with procurements. The policies identify who has the authority to enter into a contract, the limits of authority, and the processes and procedures that should be followed. Prior to conducting a procurement, the project manager and technically qualified project team members work with contracting professionals to develop the request for proposals (RFP), statement of work (SOW), terms and conditions, and other necessary documents.

The other options are incorrect because they will not typically provide specific guidance on negotiating authority.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?