A project manager has just received formal acceptance and final payment from a client for a software development project. The project manager needs to begin preparing the final project report. Which of the following will be most useful in creating the final report?
Procurement 10 soal (Chapter 12)

Quiz
•
Professional Development
•
Professional Development
•
Hard

Asma Budi Aswadi
Used 6+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Stakeholder register
Communication management plan
Project charter
Closing report register
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A vendor on your project informs you that they will be unable to perform the work as contracted after some equipment required for the project was destroyed in a hurricane. The vendor cites a clause in the contract that is designed to address the inability of party to execute their responsibilities due to extraordinary factors that were outside the control of the party. What clause does the vendor refer to?
Arbitration
Force majeure
No-contest
Termination
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are leading a project with some of the deliverables outsourced to a vendor. You have been working closely with your procurement administrator to ensure that all claims, invoices, and final payments have been finalized with the vendor. Terms and conditions of the contract have been met, and all deliverables have been accepted. What should you do next?
Notify the vendor that the contract has been completed
Finalize all activities for the project and release the project team
Conduct the final inspection of the vendor’s deliverable
Carry out a structured review of the procurement process
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is a tool or technique of the Plan Procurement Management process?
Inspection
Contract negotiation
Risk-related contract decision analysis
Data analysis
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The project manager is in discussion with vendors about their bids that came in higher than expected. Additionally, according to the vendor’s responses, none of them will be able to deliver by the deadline requested. The project manager talks to the sponsor and other key project stakeholders to see if additional funds are needed to cover the extra costs and deliver on schedule. What process is the project manager performing?
Control Costs
Control Schedule
Acquire Resources
Conduct Procurements
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
As a project manager for a small company, you have been responsible for negotiating and issuing contracts. Although your company has pre-qualified vendors, and the agreements are standard, you think the procurements should be handled by someone with more knowledge on the subject rather than the project managers. Which of the following will you recommend?
Decentralized purchasing
Centralized purchasing
Pre-qualified vendors
Supply chain management
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is planning a project to build a new apartment complex on the site of a long-abandoned airport that was closed due to illegal dumping of fuel and oil. The project manager will need to provide a regulatory agency with a detailed explanation of how the cleanup will be performed before a permit can be caused. What would be the most appropriate bid document to send to potential vendors for the environment cleanup?
Request for information (RFI)
Request for advisement (RFA)
Request for proposal (RFP)
Request for quotation (RFQ)
Create a free account and access millions of resources
Similar Resources on Quizizz
5 questions
Project Management

Quiz
•
Professional Development
10 questions
Risk 10 soal (Chapter 11)

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 3

Quiz
•
Professional Development
10 questions
Project Integration Revision

Quiz
•
Professional Development
15 questions
All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Quiz
•
Professional Development
7 questions
Quality VS Grade - Assignment

Quiz
•
Professional Development
9 questions
Project Implementation Week 2

Quiz
•
Professional Development
10 questions
Introduction to Project Management

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade