Schedule Management Terms

Quiz
•
Professional Development
•
4th Grade
•
Medium
Afghanistan Center
Used 8+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a software development project, the project manager decides that the testing phase can begin two weeks before the development phase is fully completed. What scheduling term describes this overlap?
Lag
Lead
Float
Network Diagram
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the planning of a construction project, the project manager determines that there must be a three-week gap between the completion of the foundation and the start of the framing. Which term describes this intentional delay?
Lead
Network Diagram
Float
Lag
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a marketing campaign project, the project manager uses a visual representation that shows the sequence of project activities and their dependencies. What is this tool called?
Float Chart
Network Diagram
Gantt Chart
PERT Chart
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is planning an IT infrastructure upgrade and identifies that certain tasks must be completed in a specific order due to technical requirements. For example, the servers must be installed before the software can be configured. What type of dependency is this?
Discretionary Dependency
Internal Dependency
External Dependency
Mandatory Dependency
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a product development project, the project manager decides to perform the market analysis and product design simultaneously based on team preferences, although it's not required. What type of dependency is this?
Mandatory Dependency
Discretionary Dependency
External Dependency
Internal Dependency
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a logistics project, the project manager notes that some tasks are dependent on suppliers' deliveries, which are outside the control of the project team. What type of dependency does this describe?
Mandatory Dependency
Discretionary Dependency
External Dependency
Internal Dependency
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project schedule, Task B cannot start until Task A finishes. What type of dependency relationship is this?
Finish to Start (FS)
Start to Finish (SF)
Finish to Finish (FF)
Start to Start (SS)
Create a free account and access millions of resources
Similar Resources on Wayground
7 questions
Team Development Stages

Quiz
•
4th Grade
7 questions
Conflict Resolution Techniques

Quiz
•
4th Grade
7 questions
Quality Vs. Grade

Quiz
•
4th Grade
7 questions
Maslow's Hierarchy

Quiz
•
4th Grade
7 questions
EEFs and OPAs

Quiz
•
4th Grade
7 questions
Types of Contract

Quiz
•
4th Grade
15 questions
Job Abbreviations

Quiz
•
1st - 12th Grade
7 questions
ASP-SM-Fmk

Quiz
•
KG - University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade