Schedule Management Terms

Schedule Management Terms

4th Grade

11 Qs

quiz-placeholder

Similar activities

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

Action Plan

Action Plan

1st - 5th Grade

10 Qs

7 - SAFe

7 - SAFe

1st - 7th Grade

6 Qs

Agile Mindset - 1-6

Agile Mindset - 1-6

4th Grade

10 Qs

Your Agile Knowledge

Your Agile Knowledge

KG - 5th Grade

10 Qs

EVM Basic Terminology

EVM Basic Terminology

4th Grade

6 Qs

Organizational Structures

Organizational Structures

4th Grade

7 Qs

Schedule Management Processes

Schedule Management Processes

4th Grade

7 Qs

Schedule Management Terms

Schedule Management Terms

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 8+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a software development project, the project manager decides that the testing phase can begin two weeks before the development phase is fully completed. What scheduling term describes this overlap?

Lag

Lead

Float

Network Diagram

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the planning of a construction project, the project manager determines that there must be a three-week gap between the completion of the foundation and the start of the framing. Which term describes this intentional delay?

Lead

Network Diagram

Float

Lag

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a marketing campaign project, the project manager uses a visual representation that shows the sequence of project activities and their dependencies. What is this tool called?

Float Chart

Network Diagram

Gantt Chart

PERT Chart

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is planning an IT infrastructure upgrade and identifies that certain tasks must be completed in a specific order due to technical requirements. For example, the servers must be installed before the software can be configured. What type of dependency is this?

Discretionary Dependency

Internal Dependency

External Dependency

Mandatory Dependency

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a product development project, the project manager decides to perform the market analysis and product design simultaneously based on team preferences, although it's not required. What type of dependency is this?

Mandatory Dependency

Discretionary Dependency

External Dependency

Internal Dependency

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a logistics project, the project manager notes that some tasks are dependent on suppliers' deliveries, which are outside the control of the project team. What type of dependency does this describe?

Mandatory Dependency

Discretionary Dependency

External Dependency

Internal Dependency

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project schedule, Task B cannot start until Task A finishes. What type of dependency relationship is this?

Finish to Start (FS)

Start to Finish (SF)

Finish to Finish (FF)

Start to Start (SS)

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?