Schedule Management Terms
Quiz
•
Professional Development
•
4th Grade
•
Practice Problem
•
Medium
Afghanistan Center
Used 9+ times
FREE Resource
Enhance your content in a minute
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a software development project, the project manager decides that the testing phase can begin two weeks before the development phase is fully completed. What scheduling term describes this overlap?
Lag
Lead
Float
Network Diagram
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the planning of a construction project, the project manager determines that there must be a three-week gap between the completion of the foundation and the start of the framing. Which term describes this intentional delay?
Lead
Network Diagram
Float
Lag
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a marketing campaign project, the project manager uses a visual representation that shows the sequence of project activities and their dependencies. What is this tool called?
Float Chart
Network Diagram
Gantt Chart
PERT Chart
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is planning an IT infrastructure upgrade and identifies that certain tasks must be completed in a specific order due to technical requirements. For example, the servers must be installed before the software can be configured. What type of dependency is this?
Discretionary Dependency
Internal Dependency
External Dependency
Mandatory Dependency
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a product development project, the project manager decides to perform the market analysis and product design simultaneously based on team preferences, although it's not required. What type of dependency is this?
Mandatory Dependency
Discretionary Dependency
External Dependency
Internal Dependency
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a logistics project, the project manager notes that some tasks are dependent on suppliers' deliveries, which are outside the control of the project team. What type of dependency does this describe?
Mandatory Dependency
Discretionary Dependency
External Dependency
Internal Dependency
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project schedule, Task B cannot start until Task A finishes. What type of dependency relationship is this?
Finish to Start (FS)
Start to Finish (SF)
Finish to Finish (FF)
Start to Start (SS)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
12 questions
Teaching and Learning
Quiz
•
KG - 12th Grade
12 questions
What do you want to be?
Quiz
•
2nd - 12th Grade
10 questions
PRETEST - WEBINAR TKP ANTI RADIKALISME by SAHABAT CPNS
Quiz
•
KG - Professional Dev...
10 questions
Power of Our Words: Open-Ended Questions
Quiz
•
KG - University
11 questions
Sun Grepa Wealth Prime
Quiz
•
1st - 10th Grade
10 questions
THE CRISIS OF CREDIT
Quiz
•
3rd - 4th Grade
15 questions
Rodzina Kardashianów
Quiz
•
1st - 10th Grade
10 questions
ENGLISH
Quiz
•
KG - University
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade