Schedule Management Terms

Schedule Management Terms

4th Grade

11 Qs

quiz-placeholder

Similar activities

OneDrive and Office 365

OneDrive and Office 365

KG - University

10 Qs

Child protection Policy April 16 ,2021

Child protection Policy April 16 ,2021

KG - 5th Grade

10 Qs

Start-UP Design

Start-UP Design

1st Grade - Professional Development

14 Qs

CARMA

CARMA

1st - 10th Grade

10 Qs

3D quiz

3D quiz

4th Grade

15 Qs

Teacher/Teacher Assistant Relationship

Teacher/Teacher Assistant Relationship

KG - 6th Grade

10 Qs

LCAH // Accor Live Limitless Essentials

LCAH // Accor Live Limitless Essentials

1st - 5th Grade

12 Qs

CC Quiz of the Week (Skills and Drills Week)

CC Quiz of the Week (Skills and Drills Week)

1st - 12th Grade

10 Qs

Schedule Management Terms

Schedule Management Terms

Assessment

Quiz

Professional Development

4th Grade

Practice Problem

Medium

Created by

Afghanistan Center

Used 9+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a software development project, the project manager decides that the testing phase can begin two weeks before the development phase is fully completed. What scheduling term describes this overlap?

Lag

Lead

Float

Network Diagram

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the planning of a construction project, the project manager determines that there must be a three-week gap between the completion of the foundation and the start of the framing. Which term describes this intentional delay?

Lead

Network Diagram

Float

Lag

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a marketing campaign project, the project manager uses a visual representation that shows the sequence of project activities and their dependencies. What is this tool called?

Float Chart

Network Diagram

Gantt Chart

PERT Chart

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is planning an IT infrastructure upgrade and identifies that certain tasks must be completed in a specific order due to technical requirements. For example, the servers must be installed before the software can be configured. What type of dependency is this?

Discretionary Dependency

Internal Dependency

External Dependency

Mandatory Dependency

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a product development project, the project manager decides to perform the market analysis and product design simultaneously based on team preferences, although it's not required. What type of dependency is this?

Mandatory Dependency

Discretionary Dependency

External Dependency

Internal Dependency

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a logistics project, the project manager notes that some tasks are dependent on suppliers' deliveries, which are outside the control of the project team. What type of dependency does this describe?

Mandatory Dependency

Discretionary Dependency

External Dependency

Internal Dependency

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project schedule, Task B cannot start until Task A finishes. What type of dependency relationship is this?

Finish to Start (FS)

Start to Finish (SF)

Finish to Finish (FF)

Start to Start (SS)

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?