Recap Quiz (Project Contract Management)

Recap Quiz (Project Contract Management)

Professional Development

33 Qs

quiz-placeholder

Similar activities

Geração de Energia Elétrica

Geração de Energia Elétrica

Professional Development

38 Qs

152 revision #2

152 revision #2

Professional Development

35 Qs

D 37 FACE THE CHALLENGE

D 37 FACE THE CHALLENGE

Professional Development

30 Qs

VEDA (ITI) - 02.06.2025

VEDA (ITI) - 02.06.2025

Professional Development

30 Qs

SET D - DPWH

SET D - DPWH

Professional Development

28 Qs

ELECTRICAL INSTRU & FEEDBACK CONTROL OBJCTVS

ELECTRICAL INSTRU & FEEDBACK CONTROL OBJCTVS

Professional Development

36 Qs

viscosity 1

viscosity 1

Professional Development

35 Qs

Housekeeping and extra random

Housekeeping and extra random

Professional Development

35 Qs

Recap Quiz (Project Contract Management)

Recap Quiz (Project Contract Management)

Assessment

Quiz

Engineering

Professional Development

Easy

Created by

Dave Lumbay

Used 12+ times

FREE Resource

33 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Department Order stating that PDM shall be used.

DO 133, S. 2015

DO 133, S. 2016

DO 133, S. 2017

DO 133, S. 2018

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

It is a tabulation of the number of units, capacity and type of equipment which are required in each month of contract duration.

Manpower Deployment Schedule

Equipment Utilization Schedule

Manpower Allocation

Equipment Allocation

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

_______ is predicted / projected / correlated from cumulative monthly target accomplishment in percent along the duration of the project. Inflow and outflow of cash maybe developed below the bar chart presentation.

S-Curve

Accumulative Flow

Cash Flow

None of the Above

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.

Lag

Lead

Both A and C

None of the Above

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.

Lag

Lead

Both A and C

None of the Above

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start.

Back Pass

Backward Pass

None of the Above

Forward Pass

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A simple visual diagram that represents each activity in the form of horizontal bars which are laid out in a time scaled chart. The completed portions are usually shaded / darkened, to depict activity completion.

Bar Chart

Pie Chart

Graph Chart

None of the Above

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?