Make or Buy Decision (Correction Needed)

Quiz
•
Professional Development
•
4th Grade
•
Hard
Afghanistan Center
Used 13+ times
FREE Resource
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to develop a new irrigation system in Ghazni, the project manager must decide whether to design the technology in-house or outsource it to an external engineering firm. The organization has significant expertise in agricultural technology but is currently handling multiple projects. The timeline for the irrigation system is flexible, but the budget is limited. What should the project manager do?
Design the technology in-house using the organization’s expertise
Outsource the design to ensure timely and high-quality implementation
Delay the project to balance the workload of current projects
Use a hybrid approach by designing some components in-house and outsourcing others
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a project to develop an e-commerce platform for local businesses in Farah, the project manager needs to decide whether to develop the platform internally or outsource it to a specialized software development company. The organization has a competent IT team but lacks specific e-commerce expertise. The project timeline is critical, and the budget is moderate. What should the project manager do?
Develop the platform internally to maintain control over the project
Outsource the development to leverage specialized expertise and meet the critical timeline
Train existing staff in e-commerce to handle the project internally
Purchase an off-the-shelf e-commerce solution and customize it internally
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to construct a new water supply system in Uruzgan, the project manager must decide whether to use the organization’s in-house construction team or hire an external construction firm. The in-house team has some experience with similar projects, and there is a moderate budget. The project must be completed quickly to address urgent water shortages. What should the project manager do?
Use the in-house construction team to leverage existing experience and save costs
Hire an external construction firm to ensure timely completion
Split the project tasks between the in-house team and an external firm
Reduce the scope of the project to fit the in-house team’s availability
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to develop a mobile banking application for a financial institution in Badghis, the project manager must decide whether to build the application in-house or purchase a ready-made solution. The organization has a strong IT team with experience in mobile applications but faces a tight deadline. The budget is sufficient for either option. What should the project manager do?
Build the application in-house to utilize the strong IT team
Purchase a ready-made solution to meet the tight deadline
Outsource the development to an experienced mobile app developer
Extend the deadline to allow for in-house development
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to distribute emergency relief kits in Nimroz, the project manager must decide whether to assemble the kits in-house or buy pre-assembled kits from a supplier. The organization has experience in assembling such kits but is currently focused on other urgent projects. The kits are needed urgently, and the budget is limited. What should the project manager do?
Assemble the kits in-house to maintain control over quality
Buy pre-assembled kits from a supplier to ensure timely distribution
Hire additional temporary staff to assemble the kits in-house
Delay the project until the organization can assemble the kits
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to deliver new training programs for teachers in Baghlan, the project manager must decide whether to develop the training materials in-house or hire a specialized educational firm. The organization has subject matter experts but lacks experience in creating training programs. The project has a flexible timeline but a tight budget. What should the project manager do?
Develop the training materials in-house to utilize internal subject matter experts
Hire a specialized educational firm to leverage their expertise
Split the development of training materials between in-house and external resources
Delay the project to develop in-house training expertise
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to develop new healthcare management software for a hospital in Helmand, the project manager must decide whether to build the software in-house or contract it out to a specialized software development firm. The organization has a skilled IT department but lacks experience in healthcare applications. The budget is ample, and the timeline is moderately flexible. What should the project manager do?
Build the software in-house to develop internal expertise
Contract the software development to ensure specialized expertise and high quality
Extend the project timeline to allow for in-house development
Use open-source software and customize it internally
Similar Resources on Wayground
10 questions
Quiz NestJs - 2

Quiz
•
1st - 12th Grade
6 questions
Prevention Vs. Inspection

Quiz
•
4th Grade
7 questions
Quality Management Tools

Quiz
•
4th Grade
7 questions
Team Development Stages

Quiz
•
4th Grade
6 questions
Risk Response Strategies-Negative Risks

Quiz
•
4th Grade
5 questions
4. Science Vs. Art in Project

Quiz
•
4th Grade
10 questions
Riyadh Metro Refund and Replacement Work Instruction Quiz

Quiz
•
1st - 5th Grade
10 questions
Blank Quiz 51

Quiz
•
4th Grade
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade
Discover more resources for Professional Development
20 questions
Place Value

Quiz
•
4th Grade
18 questions
Subject and Predicate Practice

Quiz
•
4th Grade
5 questions
Remembering 9/11 Patriot Day

Lesson
•
3rd - 5th Grade
20 questions
Run-On Sentences and Sentence Fragments

Quiz
•
3rd - 6th Grade
20 questions
4 Types of Sentences

Quiz
•
3rd - 5th Grade
20 questions
place value

Quiz
•
4th Grade
20 questions
Place Value and Rounding

Quiz
•
4th Grade
15 questions
Place Value

Quiz
•
4th Grade