Prep-Cast CAPM Domain#2 Predictive

Prep-Cast CAPM Domain#2 Predictive

1st Grade

10 Qs

quiz-placeholder

Similar activities

Chapt5

Chapt5

1st Grade

10 Qs

06. Schedule Management

06. Schedule Management

1st - 3rd Grade

12 Qs

001. Pre & Post Test PMP Des 2024

001. Pre & Post Test PMP Des 2024

1st Grade

12 Qs

Chapt 7

Chapt 7

1st Grade

10 Qs

PMI SH - Plan and Manage Project Compliance

PMI SH - Plan and Manage Project Compliance

1st - 3rd Grade

14 Qs

PMI-SH Manage Project/phase Closure or Transitions

PMI-SH Manage Project/phase Closure or Transitions

1st Grade

15 Qs

Communication Management

Communication Management

1st - 3rd Grade

10 Qs

training 8 aug ciast - muhaimin

training 8 aug ciast - muhaimin

1st - 5th Grade

10 Qs

Prep-Cast CAPM Domain#2 Predictive

Prep-Cast CAPM Domain#2 Predictive

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

sudiyuwono wowo

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is leading a project with a predictive life cycle. Detailed plans were provided by the requesting organization before the start of the project.

What will be the focus of the project manager?

Controlling the schedule by successively adding functionality until the deadline is reached

Controlling scope to meet schedule and budget

Determining the scope before the start of each iteration

Revising cost and time estimates as the project team's understanding of the product increases

Answer explanation

In a predictive life cycle, the project scope, time, and cost are determined in the early phases of the life cycle. Any changes to the scope are carefully managed.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have been hired midway into project execution to replace the previous project manager. The project is in disarray: discussions on changes frequently become shouting matches between the project team members, no one seems to take responsibility, and the project management plan is incomplete. As a result, the project is far behind schedule.

What is your best course of action?

Use management reserves to cover for the lost time

Seek help from the project management office (PMO)

Fire the project team members and outsource the work

Revise the project management plan and have it approved

Answer explanation

To manage the project, it is vital for you, as a project manager, to have a complete and approved project management plan.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are leading a project to renovate a sports stadium. The project has a hard deadline as the work must be completed before the start of the games season. Upon developing and optimizing the schedule, the total float for the project is negative. The project sponsor is adamant that the project must be completed on time at any cost. As you try to find the solution, you realize that none of the activities can be overlapped.

What is your best course of action?

Schedule some activities on the critical path to be performed in parallel instead of in sequence

Do nothing as negative float implies the schedule is adequate to complete the project on time

Perform resource smoothing to bring the schedule into alignment with project goals

Shorten the schedule duration by the least incremental cost by adding resources

Answer explanation

Correct. This answer choice describes the schedule compression technique known as crashing. Crashing can be used to shorten the critical path and bring the schedule into alignment with project objectives. Crashing typically results in higher costs. According to the scenario, the sponsor is not price-sensitive. Therefore, shortening the schedule duration by the least incremental cost by adding resources, i.e., crashing the schedule, is your best course of action.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After a few weeks of observation, an agile coach that was hired to guide a company through its transition from a waterfall to an agile project management approach told the company's management that the company still used waterfall methods to carry out its projects.

Which of the following did the agile coach most likely notice that led them to reach that conclusion?

A predictive life cycle was used to carry out project activities.

Project teams delivered product increments in small batch hand-offs.

Management supported empowerment and decentralized control.

A product vision statement was mandated for each project.

Answer explanation

A predictive life cycle is associated with traditional or waterfall project management. In contrast, agile life cycles are iterative and incremental in nature. Predictive life cycles expect high certainty around firm requirements, a stable team, and low risk. The usage of a predictive life cycle is an indication that the company uses waterfall methods.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A company charters a project to redesign a process used to manufacture the company products. The new process is supposed to roll out at the end of the project. To support its transition to agile, the company decides to use a two-week delivery cadence. After several sprints, the company is unpleasantly surprised to see that no business value was produced.

What, if any, mistakes did the company most likely make?

Selected an incorrect delivery cadence

Used sprints instead of iterations

Did not assign a dedicated agile coach

The company made no mistakes

Answer explanation

The scenario implies that the company selected a periodic deliveries cadence, while the project was supposed to produce a single delivery at its end - a new process. Therefore, the most likely mistake the company made was selecting an incorrect delivery cadence, making this choice the best answer for the question asked.

6.

MATCH QUESTION

1 min • 1 pt

Midway into project execution, a stakeholder approaches the project manager requesting a change to one of the project deliverables.

In what order should the project manager take the following steps to process the stakeholder's request? (Drag and drop the items from right to left.)

Evaluate the change

Step-3

Look for the alternatives

Step-2

Make a decision

Step-5

Implement the change

Step-4

Submit change request

Step-1

Answer explanation

Understanding the first step in the process of handling change requests is typically the most difficult thing for a PMP aspirant. Our team had an extensive debate on the subject of change requests and the sequence of steps involved in this process. The reason being is that the PMBOK® Guide does not do a good job of explaining the exact process in detail. We have discussed the sequence of steps among our team of certified project management professionals and have concluded that the first thing that should be done when a change is requested on a project is the physical (or digital) creation of the change request form, a document if you wish. In other words, submitting a change request, i.e., filling out a form, is the first thing that should be done when a change is requested on the project. Otherwise, on what basis would the project manager, the project team, the change control board (CCB), and other relevant stakeholders spend time evaluating a request that is not even documented?

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

A large construction project is in execution. According to the project schedule, today the project manager has individual mentoring sessions with three stakeholders that are new to the project.

When mentoring these stakeholders, which of the following project management processes might the project manager be performing? (Choose two.)

Develop Project Charter

Plan Communications Management

Identify Stakeholders

Manage Communications

Develop Team

Answer explanation

D. Feedback is among the communication techniques associated with the Manage Communications process. Feedback supports interactive communication between the project manager, team, and all other project stakeholders. Mentoring is one example of feedback that might be used in support of the Manage Communications process.

E. Mentoring is a technique that might be used as part of training a new project team member. Since project team members are stakeholders, it is possible that one or more of the new stakeholders is a member of the project team, justifying an iteration of the Develop Team process.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?