Week Two Review

Week Two Review

University

9 Qs

quiz-placeholder

Similar activities

Project Management Quiz

Project Management Quiz

University

10 Qs

Chapter 5

Chapter 5

University

10 Qs

INPM practice

INPM practice

University

6 Qs

7BUSS007C - 1

7BUSS007C - 1

University

10 Qs

DESIGN AND BUILDING TEAM

DESIGN AND BUILDING TEAM

University

10 Qs

Unit 17 Project management: Project Constraints 3

Unit 17 Project management: Project Constraints 3

12th Grade - University

11 Qs

PBO kelas 12 RPL

PBO kelas 12 RPL

University

10 Qs

17/8 Gantt Charts: Multiple Choice Quiz

17/8 Gantt Charts: Multiple Choice Quiz

12th Grade - University

11 Qs

Week Two Review

Week Two Review

Assessment

Quiz

Other

University

Hard

Created by

John MacCatherine

Used 2+ times

FREE Resource

9 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

A project is characterized by all except which one of the following

Temporary in nature

Routine and operational

Defined beginning and ending

Defined objective

Budgeted resources

2.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

The project initiation phase ends with an approved ___________

3.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

The project charter is essentially a contract between which two project stakeholders?

Project manager

Customer

User

Sponsor

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which stage of team formation often involves a significant amount of conflict?

Forming

Storming

Norming

Performing

Adjourning

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which organization structure requires people to have more than one "boss"?

Functional

Centralized

Decentralized

Matrix

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

A stakeholder is someone with a financial interest in the success of the project

True

False

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which source of power is particularly useful for project managers?

Formal

Delegated

Maniacal

Personal

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The budget for this project is $500,000.

This is an example of a/an...

Assumption

Exclusion

Constraint

Milestone

9.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Helpdesk staff will have necessary procedures to support the proposed solution

This is an example of a/an

Assumption

Constraint

Risk

Milestone