You are the project manager for the BBB Project. Stacy, a project team member, is confused about what QA is.
Which of the following best describes QA?
All-in-one CAPM/PMP: Chapter 8 - Quality
Quiz
•
Professional Development
•
Professional Development
•
Medium
Patrick Pepin
Used 3+ times
FREE Resource
Student preview
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager for the BBB Project. Stacy, a project team member, is confused about what QA is.
Which of the following best describes QA?
QA is quality assurance for the overall project performance.
QA is quality acceptance according to scope verification
QA is quality assurance for the project deliverable.
QA is quality assurance for the project stakeholders.
Answer explanation
A. QA is concerned with overall project quality performance.
B, C, and D are incorrect because they do not correctly describe quality assurance.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager for the Photo Scanning Project. This project is similar to another project you have completed. This project will electronically store thousands of photos for your city's historical society. Quality is paramount on this project. Management approaches you and asks why you have devoted so much of the project time to planning.
Your response is which of the following?
This is a first-time, first-use project, so more time is needed for planning.
Planning for a project of this size, with this amount of quality, is mandatory.
Quality is planned into a project, not inspected in.
Quality audits are part of the planning time.
Answer explanation
C. Of all the choices presented, C is the best answer. Quality is planned into the project, and the planning requires time.
A is incorrect because a project of this nature has been completed before.
B is incorrect because there isn't enough information provided to determine what the quality demands of the project are.
D is incorrect because quality audits are not part of the planning processes.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager for the recently initiated Floor Installation Project.
Today you plan to meet with your project team to discuss the fact that the project must be executed with no deviations from the project requirements.
This process is which of the following?
Quality planning
Quality management
Quality control
Quality assurance
Answer explanation
A. Quality planning should be completed prior to the work beginning and should be revisited thereafter as needed.
B is incorrect because quality management is not an applicable answer to the scenario.
C and D are incorrect because QC and QA are part of quality management.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager for the ASE Project, which must map to industry standards in order to be accepted by the customer. You and your team have studied the requirements and have created a plan to implement the deliverables with the appropriate level of quality.
What is this proces called6
Quality planning
Quality management
Quality control
Quality assurance
Answer explanation
A. Quality planning is the process of creating a plan to meet the requirements of quality.
B, C, and D are incorrect because they do not name the process in the question's scenario.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Juan is the project manager for his organization and he's asked Beth, a project team member, to help him create a fishbone diagram. Beth doesn't know what this is and asks for your help.
A fishbone diagram is the same as a(n) diagram.
Ishikawa
Pareto
Flow
Control
Answer explanation
A. A fishbone diagram is the same as an Ishikawa diagram.
B, C, and D are incorrect. These charts and diagrams accomplish goals other than the cause-and-effect outcome of the Ishikawa, or fishbone, diagram.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Management has asked you to define the correlation between quality and the project scope.
Which of the following is the best answer?
The project scope includes metrics for quality.
Quality metrics are applied to the project scope.
Quality is the process of completing the scope to meet stated or implied needs.
Quality is the process of evaluating the project scope to ensure that quality exists.
Answer explanation
C. Quality, in regard to the project scope, is about completing the work to provide the stated or implied needs, as promised.
A is incorrect because, although the project scope will have requirements for acceptance, it may not have metrics for quality defined.
B and D are incorrect statements.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager of the Condo IV Construction project and you're working with your project team and the project sponsor to identify the quality metrics and develop the quality management plan for the project.
In light of this planning event, which of the following is most true about quality?
It will cost more money to build quality into the project.
It will cost less money to build quality into the project process.
Quality is inspection-driven.
Quality is prevention-driven.
Answer explanation
D. Quality is prevention-driven. Quality means completing the work correctly the first time to prevent poor results, loss of time, and loss of funds.
A and B are incorrect. There is no guarantee that a project will cost more or less depending on the amount of expected quality. Incidentally, lack of quality will likely cost more than quality planning because of the cost of nonconformance.
C is incorrect because quality is planned into a project, not inspected in.
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade