People Domain - Start a Project

People Domain - Start a Project

Professional Development

25 Qs

quiz-placeholder

Similar activities

Business Environment Take-Home Quiz

Business Environment Take-Home Quiz

Professional Development

25 Qs

Akuntabilitas

Akuntabilitas

Professional Development

27 Qs

Corporate Governance Quiz

Corporate Governance Quiz

Professional Development

30 Qs

KVS Guidelines for School Library and Procedure Manual

KVS Guidelines for School Library and Procedure Manual

Professional Development

25 Qs

Dr.S.Uma's Principles of Management Quiz

Dr.S.Uma's Principles of Management Quiz

University - Professional Development

20 Qs

Prep Quiz 1

Prep Quiz 1

Professional Development

30 Qs

merchandising et digital

merchandising et digital

Professional Development

20 Qs

Bahtera Pop Up Quiz

Bahtera Pop Up Quiz

Professional Development

20 Qs

People Domain - Start a Project

People Domain - Start a Project

Assessment

Quiz

Social Studies

Professional Development

Hard

Created by

Cheryl Lee

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

A new Project Manager joins the Software development project during the middle of execution. Before meeting all key stakeholders, he wants to prepare a report that compares the current and desired level of engagement of stakeholders involved in the project.

What should he review to fetch this necessary information?

Stakeholder Register

Stakeholder Engagement assessment matrix

Stakeholder Engagement plan

Communication Management Plan

Answer explanation

As per the question, the Project Manager should consult the Stakeholder Engagement assessment matrix to compare the Stakeholder's current and desired level of engagement. Some may get confused with Stakeholder Engagement Plan, but the Stakeholder Engagement Plan documents "how the adjustments to stakeholders' level of engagement will be achieved".

2.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

You are a Project Manager of XYZ company. You are currently performing Stakeholder Analysis for an upcoming project to align expectations and gain support for the project. The initial list of Key Stakeholders is first time identified as a part of which process?

Develop Project Charter

Stakeholder Register

Business Case

Stakeholder Engagement plan

Answer explanation

The question here asks about the process that fetches the  initial list of key stakeholders.

Choice A - Develop Project Charter - Correct - Project Charter, the main output of Develop Project Charter process contains key stakeholder list and high level classification of roles and responsibilities of everyone involved in the project.

Choice  B - Stakeholder Register - Incorrect - It is an example of a Project Document that records all Stakeholder information.

Choice C - Business Case -  Incorrect - It is a Business Document which is input for the Develop Project Charter process. Business case justifies why the project was undertaken.

Choice D - Stakeholder Engagement plan - Incorrect - It is an output for the Plan Stakeholder Engagement Process. It provides actionable plan to interact effectively with the stakeholders.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 81, 509.

3.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

A project manager has just finished a project charter and received approval from the project sponsor. The project manager then presented the project charter to the stakeholders and noticed a lack of participation from some of them during this meeting.

What should the project manager do?

Ask the project team to monitor these stakeholders and their involvement

Include this in the risk register because the Project Manager is uncertain that the stakeholders understand their responsibilities in this project

Report the concerns about the stakeholders' lack of involvement to the project sponsor

Hold one-on-one meetings with these stakeholders to ensure their understanding of key deliverables and their responsibilities

Answer explanation

Every stakeholder needs to understand the deliverables and their responsibilities towards the project. The project manager should address this immediately.

The other answer choices are incorrect. It is not a risk to be recorded in the risk register but an issue for the project manager to resolve. The project manager is responsible for ensuring that the stakeholders are involved in the project. Reporting the concern to the project sponsor will not resolve the problem of stakeholder engagement. It is not the responsibility of the project team to monitor the stakeholders. It needs to be done by the project manager.

The correct answer(s)

Hold one-on-one meetings with these stakeholders to ensure their understanding of key deliverables and their responsibilities.

4.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

Good Interpersonal skills play a phenomenal role in successful stakeholder engagement.

All of the following are examples of interpersonal skills EXCEPT:

Resisting to change

Building trust

Resolving Conflict

Active listening

Answer explanation

Resisting to change is not a valid interpersonal skill.

(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 144-145, 153, 709.

5.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

As a Project Manager, you are updating the Stakeholder Register to include three Specialists who have just joined your project temporarily to implement a Business-critical task that involves Pure Risk.

How will the newly appointed specialists be classified in the Stakeholder Register based on their direction of influence in the project?

3 Specialists will be marked as Outward in the Stakeholder Register

3 Specialists will be marked as Sideward in the Stakeholder Register

3 Specialists will be marked as Downward in the Stakeholder Register

3 Specialists will be marked as Influential in the Power/Interest grid

Answer explanation

The question implies that the three specialists are hired temporarily to complete important project work. It suggests that their Direction of Influence in the project is Downward as they can influence the project with their specialized knowledge in a temporary capacity.

   (PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 513.

6.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

A salience model is a combination of which  of the following stakeholder characteristics?

Power, Interest, and Involvement

Influence, Impact, and Interest

Power, influence, and impact

Urgency, Power, and Legitimacy

Answer explanation

(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 513.

7.

MULTIPLE CHOICE QUESTION

1 min • 10 pts

Troy is a Project Manager of a complex automation project which is currently under planning. In a meeting with the Project team to determine initial Stakeholder communication strategies, Troy sees that the Team has done well in stakeholder analysis and grouped stakeholders based on Power-Interest-Attitude.

What does this signify?

Team has prepared Power/Interest grid to map identified stakeholders in a project.

Team has prepared Stakeholder Cube to classify stakeholders on the basis of Power, Interest, and Attitude.

Team has used Data analysis tool to classify stakeholders according to their direction of influence.

Team has prepared Salience model to classify Stakeholders based on Power, Interest, Attitude.

Answer explanation

The Question states that Team has prepared the Stakeholder Cube. The Power-Interest grid has two axes, and if you add the 3rd axis, you’ll get a Cube. Here Attitude is the third axis added to the Power-Interest grid. Stakeholder Cube is the refinement of the grid model, which combines the grid elements into a three-dimensional model that can help the Project Team develop Stakeholder communication strategies.

(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 513.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?