People Domain - Start a Project

Quiz
•
Social Studies
•
Professional Development
•
Hard
Cheryl Lee
FREE Resource
25 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
A new Project Manager joins the Software development project during the middle of execution. Before meeting all key stakeholders, he wants to prepare a report that compares the current and desired level of engagement of stakeholders involved in the project.
What should he review to fetch this necessary information?
Stakeholder Register
Stakeholder Engagement assessment matrix
Stakeholder Engagement plan
Communication Management Plan
Answer explanation
As per the question, the Project Manager should consult the Stakeholder Engagement assessment matrix to compare the Stakeholder's current and desired level of engagement. Some may get confused with Stakeholder Engagement Plan, but the Stakeholder Engagement Plan documents "how the adjustments to stakeholders' level of engagement will be achieved".
2.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
You are a Project Manager of XYZ company. You are currently performing Stakeholder Analysis for an upcoming project to align expectations and gain support for the project. The initial list of Key Stakeholders is first time identified as a part of which process?
Develop Project Charter
Stakeholder Register
Business Case
Stakeholder Engagement plan
Answer explanation
The question here asks about the process that fetches the initial list of key stakeholders.
Choice A - Develop Project Charter - Correct - Project Charter, the main output of Develop Project Charter process contains key stakeholder list and high level classification of roles and responsibilities of everyone involved in the project.
Choice B - Stakeholder Register - Incorrect - It is an example of a Project Document that records all Stakeholder information.
Choice C - Business Case - Incorrect - It is a Business Document which is input for the Develop Project Charter process. Business case justifies why the project was undertaken.
Choice D - Stakeholder Engagement plan - Incorrect - It is an output for the Plan Stakeholder Engagement Process. It provides actionable plan to interact effectively with the stakeholders.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 81, 509.
3.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
A project manager has just finished a project charter and received approval from the project sponsor. The project manager then presented the project charter to the stakeholders and noticed a lack of participation from some of them during this meeting.
What should the project manager do?
Ask the project team to monitor these stakeholders and their involvement
Include this in the risk register because the Project Manager is uncertain that the stakeholders understand their responsibilities in this project
Report the concerns about the stakeholders' lack of involvement to the project sponsor
Hold one-on-one meetings with these stakeholders to ensure their understanding of key deliverables and their responsibilities
Answer explanation
Every stakeholder needs to understand the deliverables and their responsibilities towards the project. The project manager should address this immediately.
The other answer choices are incorrect. It is not a risk to be recorded in the risk register but an issue for the project manager to resolve. The project manager is responsible for ensuring that the stakeholders are involved in the project. Reporting the concern to the project sponsor will not resolve the problem of stakeholder engagement. It is not the responsibility of the project team to monitor the stakeholders. It needs to be done by the project manager.
The correct answer(s)
Hold one-on-one meetings with these stakeholders to ensure their understanding of key deliverables and their responsibilities.
4.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Good Interpersonal skills play a phenomenal role in successful stakeholder engagement.
All of the following are examples of interpersonal skills EXCEPT:
Resisting to change
Building trust
Resolving Conflict
Active listening
Answer explanation
Resisting to change is not a valid interpersonal skill.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 144-145, 153, 709.
5.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
As a Project Manager, you are updating the Stakeholder Register to include three Specialists who have just joined your project temporarily to implement a Business-critical task that involves Pure Risk.
How will the newly appointed specialists be classified in the Stakeholder Register based on their direction of influence in the project?
3 Specialists will be marked as Outward in the Stakeholder Register
3 Specialists will be marked as Sideward in the Stakeholder Register
3 Specialists will be marked as Downward in the Stakeholder Register
3 Specialists will be marked as Influential in the Power/Interest grid
Answer explanation
The question implies that the three specialists are hired temporarily to complete important project work. It suggests that their Direction of Influence in the project is Downward as they can influence the project with their specialized knowledge in a temporary capacity.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 513.
6.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
A salience model is a combination of which of the following stakeholder characteristics?
Power, Interest, and Involvement
Influence, Impact, and Interest
Power, influence, and impact
Urgency, Power, and Legitimacy
Answer explanation
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 513.
7.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Troy is a Project Manager of a complex automation project which is currently under planning. In a meeting with the Project team to determine initial Stakeholder communication strategies, Troy sees that the Team has done well in stakeholder analysis and grouped stakeholders based on Power-Interest-Attitude.
What does this signify?
Team has prepared Power/Interest grid to map identified stakeholders in a project.
Team has prepared Stakeholder Cube to classify stakeholders on the basis of Power, Interest, and Attitude.
Team has used Data analysis tool to classify stakeholders according to their direction of influence.
Team has prepared Salience model to classify Stakeholders based on Power, Interest, Attitude.
Answer explanation
The Question states that Team has prepared the Stakeholder Cube. The Power-Interest grid has two axes, and if you add the 3rd axis, you’ll get a Cube. Here Attitude is the third axis added to the Power-Interest grid. Stakeholder Cube is the refinement of the grid model, which combines the grid elements into a three-dimensional model that can help the Project Team develop Stakeholder communication strategies.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 513.
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
8710 unit 4

Quiz
•
Professional Development
20 questions
Latihan Evaluasi MOOC 4

Quiz
•
Professional Development
24 questions
Introdução à Gestão de Projetos

Quiz
•
Professional Development
20 questions
Cinema Quizz

Quiz
•
Professional Development
21 questions
3.6.3 Improving Organisational Design

Quiz
•
Professional Development
20 questions
World Affairs

Quiz
•
Professional Development
21 questions
Diagnosa Organisasi

Quiz
•
Professional Development
25 questions
Pre-UAS SKBD

Quiz
•
University - Professi...
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade