A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end. What action should the project manager take to motivate the project team’s performance?

Blank Quiz 125

Quiz
•
Professional Development
•
4th Grade
•
Hard
Afghanistan Center
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Send a formal notice to team members instructing them to maintain performance
Hire a few temporary team members to help with the additional work
Award certificates of appreciation to encourage the team
Inform the team about the delivery pressure from the project sponsor
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished.What should the project manager have done differently?
Formed a separate quality assurance team to test all items coming from each team at the end of each sprint
Performed a Scrum of Scrums on a regular basis to help the teams remove impediments
Ensured frequent and continuous integration of work to obtain early feedback and continuous learning
Arranged an online session on the integration concept and suggested tools to the teams
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork.What should the project manager do to improve morale?
Identify the wants and aspirations of the team
Build team connections and emotional bonds
Forge consensus through team participation.
Set goals and push the team to achieve the goals
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A software project using an agile approach is facing quality issues with every release,generating many production problems.What should the project manager do to fix the problem and improve the quality?
Seek extra funding approval with the sponsor to replace junior team members for more experienced ones
Create a reward system granting incentives to the team members who are able to catch more defects
Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.
Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project. What should the project manager do first?
Develop the resource management plan and ensure adequate training
Replace the current project team members
Outsource the task to be completed by a specialized vendor.
Update the issue log to account for the lack of team member qualifications
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?
A release burndown chart
Analysis of the business requirements document
Story points for the remaining user stories
Surrogate measurements
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint What should the project manager have done to avoid this situation?
Involved the key stakeholders in the decision-making process
Customized stakeholder communications based on the stakeholders’ needs
Analyzed the changes in stakeholder attributes
Documented the project vision and objectives
Create a free account and access millions of resources
Similar Resources on Quizizz
8 questions
Schedule Compression & Optimization

Quiz
•
4th Grade
12 questions
W.6 TA3 Workplace Meeting

Quiz
•
3rd Grade - University
8 questions
Project Management Methodologies

Quiz
•
4th Grade
7 questions
1. PMP Sample Questions

Quiz
•
4th Grade
8 questions
Cost Management Terminology

Quiz
•
4th Grade
10 questions
3. Definition of Project

Quiz
•
4th Grade
7 questions
Organizational Structures

Quiz
•
4th Grade
8 questions
Estimation Techniques

Quiz
•
4th Grade
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade