Blank Quiz 125

Blank Quiz 125

4th Grade

12 Qs

quiz-placeholder

Similar activities

Conflict Resolution Techniques

Conflict Resolution Techniques

4th Grade

7 Qs

Maslow's Hierarchy

Maslow's Hierarchy

4th Grade

7 Qs

IT QUIZ

IT QUIZ

1st - 12th Grade

15 Qs

EEFs and OPAs

EEFs and OPAs

4th Grade

7 Qs

ASP-SM-Fmk

ASP-SM-Fmk

KG - University

7 Qs

Organizational Structures

Organizational Structures

4th Grade

7 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

Team Development Stages

Team Development Stages

4th Grade

7 Qs

Blank Quiz 125

Blank Quiz 125

Assessment

Quiz

Professional Development

4th Grade

Hard

Created by

Afghanistan Center

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end. What action should the project manager take to motivate the project team’s performance?

Send a formal notice to team members instructing them to maintain performance

Hire a few temporary team members to help with the additional work

Award certificates of appreciation to encourage the team

Inform the team about the delivery pressure from the project sponsor

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished.What should the project manager have done differently?

Formed a separate quality assurance team to test all items coming from each team at the end of each sprint

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments

Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

Arranged an online session on the integration concept and suggested tools to the teams

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork.What should the project manager do to improve morale?

Identify the wants and aspirations of the team

Build team connections and emotional bonds

Forge consensus through team participation.

Set goals and push the team to achieve the goals

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A software project using an agile approach is facing quality issues with every release,generating many production problems.What should the project manager do to fix the problem and improve the quality?

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

Create a reward system granting incentives to the team members who are able to catch more defects

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project. What should the project manager do first?

Develop the resource management plan and ensure adequate training

Replace the current project team members

Outsource the task to be completed by a specialized vendor.

Update the issue log to account for the lack of team member qualifications

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?

A release burndown chart

Analysis of the business requirements document

Story points for the remaining user stories

Surrogate measurements

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint What should the project manager have done to avoid this situation?

Involved the key stakeholders in the decision-making process

Customized stakeholder communications based on the stakeholders’ needs

Analyzed the changes in stakeholder attributes

Documented the project vision and objectives

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?