Module 1 CAPM (part 2)

Module 1 CAPM (part 2)

Professional Development

18 Qs

quiz-placeholder

Similar activities

Labor Relations and Negotations 1

Labor Relations and Negotations 1

University - Professional Development

15 Qs

Schedule Management Plan

Schedule Management Plan

Professional Development

15 Qs

02. Quiz Sosialisasi

02. Quiz Sosialisasi

Professional Development

15 Qs

vCTC Christmas in July

vCTC Christmas in July

KG - Professional Development

16 Qs

Pengertian Wirausaha dan wirausahawan

Pengertian Wirausaha dan wirausahawan

12th Grade - Professional Development

20 Qs

Insulin Launch Quiz

Insulin Launch Quiz

Professional Development

18 Qs

GE102 - Midterm Quiz

GE102 - Midterm Quiz

Professional Development

16 Qs

Telangana cuisine

Telangana cuisine

Professional Development

17 Qs

Module 1 CAPM (part 2)

Module 1 CAPM (part 2)

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Moldy Maulana

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In Functional Organization, who has the most authority to manage the projects?

Project Manager

Funtional Manager

Project Management Administrative staff

Employees

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which type of organizational structure is characterized by project managers having full responsibility for the budget of their projects?

Funtional

Virtual

Project-Oriented

Multi-divisional

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the primary objective of a project manager in predictive environments?

Achieving high-level requirements

Completing the project on time and within budget

Providing detailef risk management

Fostering teamwork among stakeholder

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When is it better for the project manager to involve the project?

During the initiation phase

after the completion of the project

after the creation of project management plan

Before the initiation phase

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Who are considered stakeholders in a project?

Only Project team members

Individual outside the organization

Anyone who affects the project or is affected by it

only the project manager and project sponsor

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What are the major responsibilities of a project sponsor?

Managing detailed risk and issues

Financing the project and preventing unnecessary changes

Managing the projecr team and resources

Approving detailed project plans and schedules

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

How does the project sponsor's role differ from that of the project manager?

The Project Sponsor provides finance while the project manager manage the budget

The project sponsor is responsible for creating the project management plan, while the project manager assists

The Project sponsor is technical expert, while the project manager is the leader

The project sponsor manages risks, while the Project Managers the schedule

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?