A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Quiz8

Quiz
•
Professional Development
•
1st Grade
•
Hard
Afghanistan Center
FREE Resource
26 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Rebaseline the project schedule to absorb the delay.
Report the delay with rectifying actions to the project management office (PMO).
Notify the project steering committee about the cause of the delay.
Report the delay with rectifying actions to the change control board (CCB) for review.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
Revise the project schedule and inform the stakeholders regarding any delays
Revise the project estimates and meet with the project team to discuss delays
Review the management reserve to identify any costs associated with the delays
Review the contingency reserve to identify any delays to the project
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should an agile lead do to ensure their team is set up for success?
Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level
Schedule sprint meetings and coaching sessions to discuss project-related information
Plan quarterly informal meetings or team bonding sessions to encourage the team to work together
Document team tasks and challenges in order to understand when to step in and help a member of the team
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A new systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document. What should the project manager do to avoid a delay in the project?
Ask the accounting manager to delegate a team member who can support the project.
Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed.
Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource.
Begin discussions with other functional managers and meet with the accounting manager later.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process, What should the project manager do?
Descope low-priority features that were not explicitly requested and add this feature as a high priority.
Inform the senior manager that they will need a new project management plan for this feature.
Complete the most current feature and release the resources for the new feature.
Analyze the impact of this change and present the options to the senior manager.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project execution the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are only a few sprints remaining. What should the project manager do?
Work with the team to understand and solve the issues
Provide testing training to all the project team members
Increase the sprint duration so the testing can be completed
Add a new resource with testing skills to the team
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs. How should the project manager ensure the work continues smoothly?
Postpone the required work on the project until school holidays begin
Advise the school to close for the duration of the project work
Continue the work as planned and inform the school when the project team arrives on-site
Liaise with the school to include nonworking project hours during school start and finish times
Create a free account and access millions of resources
Similar Resources on Quizizz
23 questions
RMP - 4. RISK ANALYSIS

Quiz
•
1st Grade
24 questions
PMI SH - Evaluate and Address External Business Environment Chan

Quiz
•
1st - 3rd Grade
30 questions
Program Benefits Management

Quiz
•
1st Grade
30 questions
open assessment 3

Quiz
•
1st Grade
25 questions
DINING

Quiz
•
1st Grade
30 questions
Project Management Part 2

Quiz
•
1st Grade
30 questions
CRT 261

Quiz
•
1st Grade
22 questions
Microsoft 98-365 Server Admin Part 2

Quiz
•
KG - Professional Dev...
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade
Discover more resources for Professional Development
10 questions
American Flag

Quiz
•
1st - 2nd Grade
10 questions
Identifying equations

Quiz
•
KG - University
25 questions
2.4A Add Subtract within 20 quickly: set 3

Quiz
•
1st - 3rd Grade
15 questions
Music 2016

Quiz
•
KG - 12th Grade
12 questions
Summer Trivia

Quiz
•
1st - 5th Grade
44 questions
logos

Quiz
•
KG - University
20 questions
Guess that Disney

Quiz
•
KG - 5th Grade
20 questions
Cartoon Characters!

Quiz
•
KG - 5th Grade