
Quiz8

Quiz
•
Professional Development
•
1st Grade
•
Hard
Afghanistan Center
FREE Resource
26 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?
Rebaseline the project schedule to absorb the delay.
Report the delay with rectifying actions to the project management office (PMO).
Notify the project steering committee about the cause of the delay.
Report the delay with rectifying actions to the change control board (CCB) for review.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
Revise the project schedule and inform the stakeholders regarding any delays
Revise the project estimates and meet with the project team to discuss delays
Review the management reserve to identify any costs associated with the delays
Review the contingency reserve to identify any delays to the project
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should an agile lead do to ensure their team is set up for success?
Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level
Schedule sprint meetings and coaching sessions to discuss project-related information
Plan quarterly informal meetings or team bonding sessions to encourage the team to work together
Document team tasks and challenges in order to understand when to step in and help a member of the team
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A new systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document. What should the project manager do to avoid a delay in the project?
Ask the accounting manager to delegate a team member who can support the project.
Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed.
Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource.
Begin discussions with other functional managers and meet with the accounting manager later.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process, What should the project manager do?
Descope low-priority features that were not explicitly requested and add this feature as a high priority.
Inform the senior manager that they will need a new project management plan for this feature.
Complete the most current feature and release the resources for the new feature.
Analyze the impact of this change and present the options to the senior manager.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project execution the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are only a few sprints remaining. What should the project manager do?
Work with the team to understand and solve the issues
Provide testing training to all the project team members
Increase the sprint duration so the testing can be completed
Add a new resource with testing skills to the team
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs. How should the project manager ensure the work continues smoothly?
Postpone the required work on the project until school holidays begin
Advise the school to close for the duration of the project work
Continue the work as planned and inform the school when the project team arrives on-site
Liaise with the school to include nonworking project hours during school start and finish times
Create a free account and access millions of resources
Similar Resources on Wayground
25 questions
Komputer 2

Quiz
•
1st - 12th Grade
24 questions
FM - Ch -1&2

Quiz
•
1st Grade
21 questions
RMP - 5. RISK RESPONSE

Quiz
•
1st Grade
21 questions
CS Severity Level - Pre Test

Quiz
•
1st - 3rd Grade
30 questions
system app n product

Quiz
•
1st - 3rd Grade
27 questions
AM Product Owner

Quiz
•
1st Grade
30 questions
Modul 4 - IL Induction Training

Quiz
•
1st - 10th Grade
30 questions
How well do you know your colleagues?

Quiz
•
1st - 5th Grade
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade
Discover more resources for Professional Development
20 questions
addition

Quiz
•
1st - 3rd Grade
20 questions
Subject and predicate in sentences

Quiz
•
1st - 3rd Grade
20 questions
Addition and Subtraction facts

Quiz
•
1st - 3rd Grade
20 questions
Place Value

Quiz
•
KG - 3rd Grade
10 questions
Exploring Properties of Matter

Interactive video
•
1st - 5th Grade
10 questions
Odd and even numbers

Quiz
•
1st - 2nd Grade
10 questions
Exploring the 5 Regions of the United States

Interactive video
•
1st - 5th Grade
7 questions
Parts of Speech

Lesson
•
1st - 12th Grade