1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The project team is currently working on a project to upgrade all the servers across the organization. Before they were able to receive the financial server, the vendor called and said the server delivery has been delayed by 2 weeks. What document should the project manager update immediately?

Work breakdown structure

Change request

Project Schedule

Issue log

Answer explanation

The project manager should update the issue log to document the server delivery delay. This log tracks problems affecting the project, ensuring the team is aware of the impact on the project schedule.

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

While a project manager is working with the team to complete the office redesign project, a sponsor asks her to finish it 2 weeks sooner. The project manager plans to add 4 new people to the team to get the work done sooner. What technique is best described in this scenario?

Critical Path Method

Fast Tracking

Crashing

Schedule variance

Answer explanation

The project manager is adding resources to expedite project completion, which is known as Crashing. This technique involves allocating additional resources to shorten the project duration.

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The project team has completed the scope baseline and have started to break down the work packages into individual activities. What process should the team do next?

Define Scope

Create WBS

Develop Schedule

Sequence Activities

Answer explanation

After completing the scope baseline and breaking down work packages, the next step is to Sequence Activities. This involves determining the order of activities to ensure efficient project execution.

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

While monitoring and controlling a project, the project manager has been comparing the work performance data to the project management plan to see if there is any variance. What process did the project manager finish to get the work performance data?

Monitor and control project work

Monitor scope

Direct and manage project work

Control scope

Answer explanation

The project manager obtained work performance data by completing the 'Direct and manage project work' process, which involves executing the project management plan and producing the necessary performance data for monitoring.

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

While trying to determine the schedule for the project, the project manager has been informed by the team that each line of code will take about 15-45 minutes to write and debug. The application will include 1 million lines of code. What schedule estimating technique best describes this estimate?

Top-down

Bottom-up

Parametric

Analogous

Answer explanation

The estimate is based on a formula using the number of lines of code and the time per line, which fits the parametric estimating technique. This method uses statistical relationships to calculate project duration.

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The project manager is having a very difficult time collecting the requirements from the customers. The customers can't seem to put the requirements into a logical grouping. What tool can best help them group the requirements?

Prototype

Decomposition

Requirements Documentation

Affinity Diagram

Answer explanation

The Affinity Diagram is a tool that helps organize ideas and requirements into logical groups, making it easier for customers to visualize and categorize their needs. This is why it is the best choice for grouping requirements.

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The project team has completed the server deployment project. They have tested the server to ensure that it works according to the requirements that were given to them, and it seems to be functioning correctly. What process group has the team just completed?

Closing

Planning

Executing

Monitoring and Controlling

Answer explanation

The team has completed the server deployment and confirmed it meets requirements, indicating they have executed the project tasks. Therefore, the correct process group they have just completed is Executing.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?