Mastering Critical Path Analysis

Mastering Critical Path Analysis

12th Grade

10 Qs

quiz-placeholder

Similar activities

Edexcel Bus: 3.3.4 Critical Path Analysis (CPA)

Edexcel Bus: 3.3.4 Critical Path Analysis (CPA)

12th Grade

15 Qs

24-25Critical Path Test Prep

24-25Critical Path Test Prep

9th - 12th Grade

7 Qs

Networks and Critical Path Analysis

Networks and Critical Path Analysis

12th Grade

10 Qs

IS 111 Quiz No. 2.1 Staffing

IS 111 Quiz No. 2.1 Staffing

12th Grade - University

14 Qs

Invest in Yourself

Invest in Yourself

9th - 12th Grade

15 Qs

PM1 1.04 Quiz

PM1 1.04 Quiz

9th - 12th Grade

15 Qs

BTEC UNIT 19: INTRODUCING PROJECT MANAGEMENT - LA C

BTEC UNIT 19: INTRODUCING PROJECT MANAGEMENT - LA C

12th Grade

14 Qs

Critical Path Analysis Quiz

Critical Path Analysis Quiz

12th Grade

8 Qs

Mastering Critical Path Analysis

Mastering Critical Path Analysis

Assessment

Quiz

Business

12th Grade

Easy

Created by

Vinodkumar KJ

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is float time in project management?

Float time is the amount of time a task can be delayed without affecting the project's deadline.

Float time refers to the time taken for project meetings.

Float time is the total time required to complete a project.

Float time is the time allocated for team breaks during a project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do you calculate total float for an activity?

LFT+Duration+EST

LFT-Duration+EST

LFT+Duration-EST

LFT-Duration-EST

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of float time in scheduling?

Float time is used to determine project costs.

Float time only applies to resource allocation.

Float time is significant as it allows for flexibility in task scheduling without impacting project deadlines.

Float time is irrelevant to project scheduling.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a network diagram, what does a critical path represent?

The shortest path through a project network that determines the longest possible project duration.

A path that has no dependencies and can be completed at any time.

The longest path through a project network that determines the shortest possible project duration.

A path that includes all tasks in the project regardless of their duration.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do you identify the critical path in a project?

The critical path is identified by determining the longest sequence of dependent tasks that must be completed on time for the project to finish on schedule.

The critical path is the shortest sequence of tasks in a project.

The critical path is identified by random selection of tasks.

The critical path is determined by the number of resources allocated to each task.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the formula for calculating free float?

EST of previous activity - duration - EST of the next activity

EST of next activity - duration - EST of the previous activity

EST of next activity +EST of the previous activity

EST of next activity + duration + EST of the previous activity

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Explain the difference between total float and free float.

Free float is the total time a project can be delayed without affecting its budget.

Total float and free float are interchangeable terms used in project management.

Total float refers to the total time a project can be delayed without any consequences.

Total float is the total delay possible without affecting project completion; free float is the delay possible without affecting subsequent tasks.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?