Acceleration Claims in Construction

Acceleration Claims in Construction

University

18 Qs

quiz-placeholder

Similar activities

Construction Claims Quiz

Construction Claims Quiz

University

16 Qs

Causes of Construction Claims

Causes of Construction Claims

University

18 Qs

Financial

Financial

University

20 Qs

SOGA

SOGA

University

21 Qs

Ch.11 CommonLaw Contract Defs & Perf.

Ch.11 CommonLaw Contract Defs & Perf.

University

18 Qs

ERP 1

ERP 1

University - Professional Development

15 Qs

PM - Chapter 5

PM - Chapter 5

University

18 Qs

Tutorial 4 - Option for organizing business

Tutorial 4 - Option for organizing business

University

20 Qs

Acceleration Claims in Construction

Acceleration Claims in Construction

Assessment

Quiz

Business

University

Hard

Created by

Prashanth Sreram

FREE Resource

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What does an "acceleration claim" in a construction project typically refer to?

A contractor's claim for increased time to complete the project

A contractor's claim for additional costs due to speeding up the work

A claim for additional payments due to labor strikes

A claim for damages caused by delayed project completion

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is a common cause for a contractor to make an acceleration claim?

Delays caused by the contractor's own inefficiency

A directive from the project owner to speed up the work

Unforeseen site conditions

Lack of necessary materials on site

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following best describes "constructive acceleration"?

When the contractor accelerates work without being directed by the owner

When the contractor accelerates work due to delays caused by the owner

When the project is completed ahead of the original schedule

When the owner compensates the contractor for delayed work

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

When a contractor is forced to accelerate work, which of the following costs may be claimed in an acceleration claim?

Additional labor costs for overtime work

Additional equipment rental costs

Increased material costs due to faster procurement

All of the above

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is typically required for a contractor to substantiate an acceleration claim?

A formal notice from the project owner

Proof of increased costs due to accelerated work

An updated project schedule showing the acceleration

A change order from the owner

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is a potential effect of acceleration on a construction project?

Reduced project costs

Increased risk of quality issues

Increased project duration

Lower labor costs

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following actions by the project owner can lead to an acceleration claim?

Issuing a change order that significantly alters the scope

Directing the contractor to expedite work to meet deadlines

Delaying project decisions, causing the contractor to catch up

All of the above

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Business