PC12 Mock Exam

PC12 Mock Exam

12th Grade

21 Qs

quiz-placeholder

Similar activities

bandsaw safety quiz

bandsaw safety quiz

9th - 12th Grade

18 Qs

Construction Drawing Quiz 102 A

Construction Drawing Quiz 102 A

12th Grade

20 Qs

Level 2 Cold Water Plumbing Exam - Version 2

Level 2 Cold Water Plumbing Exam - Version 2

12th Grade - University

18 Qs

Construction Math Definitions

Construction Math Definitions

6th Grade - University

19 Qs

End of unit H&S Brick

End of unit H&S Brick

12th Grade

20 Qs

306 hot water systems 2 Quiz

306 hot water systems 2 Quiz

2nd Grade - University

20 Qs

unit 101 ppt 1 knowledge check

unit 101 ppt 1 knowledge check

12th Grade - University

17 Qs

Plumbing Processes PPT 2 - Power Tools

Plumbing Processes PPT 2 - Power Tools

12th Grade - University

25 Qs

PC12 Mock Exam

PC12 Mock Exam

Assessment

Quiz

Construction

12th Grade

Practice Problem

Medium

Created by

Tom Robinson

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the process called when a project manager examines historical data to predict future project outcomes?

Trend Analysis

Data Mining

Predictive Modelling

Risk Assessment

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which method listed can be used to make progress analysis easier?

Gantt Charts
Statistical Process Control
Earned Value Analysis
Risk Matrix

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project's earned value (EV) = £1100, actual cost (AC) = £600, and planned value (PV) = £800. What is the cost variance (CV)?

£400
£500
£600
£700

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The earned value report of the project shows CPI = 1.2, PV = £500,000, SV = -£220,000. What is the cost variance of the project?

£100,000
£220,000
£300,000
£400,000

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the median of the following numbers? 13, 13, 13, 13, 14, 14, 16, 18, 21

13
14
15
16

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Assuming that the current level of progress is as planned, what can you say about the out-turn?

It will be delayed
It will be on time and within budget
There will be cost overruns
Additional resources will be required

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Complete this sentence: Planned value (PV) is also known as __________

Earned Value
Forecasted Value
Budgeted Cost of Work Scheduled
Actual Cost

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?