Software Project Management Quiz

Software Project Management Quiz

University

15 Qs

quiz-placeholder

Similar activities

Software Requirement Engineering - Chapter 3 - Elicitation

Software Requirement Engineering - Chapter 3 - Elicitation

University

20 Qs

Q1 Role and Skill of System Analyst & Key Skills_Quiz 1

Q1 Role and Skill of System Analyst & Key Skills_Quiz 1

University

20 Qs

SEPM Sample MCQs

SEPM Sample MCQs

University

15 Qs

The Role of IETF & Network Protocols

The Role of IETF & Network Protocols

10th Grade - University

15 Qs

Problem Solving and Programming Design (Part 2)

Problem Solving and Programming Design (Part 2)

University

15 Qs

AI Knowledge Quiz

AI Knowledge Quiz

University

16 Qs

Informatika

Informatika

10th Grade - University

10 Qs

Understanding Database Management Systems

Understanding Database Management Systems

12th Grade - University

10 Qs

Software Project Management Quiz

Software Project Management Quiz

Assessment

Quiz

Information Technology (IT)

University

Hard

Created by

NORMI STAFF

Used 2+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The first step in project planning is to?

Determine the budget

Select a team organizational model

determine the project constraints

establish the objectives and scope

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Effective software project management focuses on four P's which are

people, performance, payoff, product

people, performance, process, product

people, performance, project, product

people, process, payoff, product

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project, it refers to a roadmap of all activities to be done with specified order and within time slot allotted to each activity.

project scheduling

project estimation

monitoring

scope management

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It defines the scope of a project and is essential because it creates boundaries by clearly defining what would be done and what would not be done.

project scheduling

project estimation

monitoring

scope management

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It is said to be an intangible product.

software

hardware

monitoring

scope management

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It can be estimated in terms of KLOC.

software size estimation

efforts estimation

cost estimation

hardware estimation

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project managers estimate it in terms of personnel requirement and man-hour required to produce the software.

software size estimation

efforts estimation

cost estimation

hardware estimation

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?