Heating

Heating

Professional Development

5 Qs

quiz-placeholder

Similar activities

Maszyny i faktury stasowane w kamieniarstwie.

Maszyny i faktury stasowane w kamieniarstwie.

Professional Development

10 Qs

Power Delivery System Quiz

Power Delivery System Quiz

Professional Development

10 Qs

CHAPTER 6

CHAPTER 6

Professional Development

10 Qs

CHAPTER 3(NPCP)

CHAPTER 3(NPCP)

Professional Development

10 Qs

Rubber Insulating Equipment Testing Quiz

Rubber Insulating Equipment Testing Quiz

Professional Development

10 Qs

Rubber Insulating Equipment Testing Quiz

Rubber Insulating Equipment Testing Quiz

Professional Development

9 Qs

Project Management (Pre-Test)

Project Management (Pre-Test)

Professional Development

6 Qs

October Sales Meeting Quiz

October Sales Meeting Quiz

Professional Development

10 Qs

Heating

Heating

Assessment

Quiz

Construction

Professional Development

Hard

Created by

Dedy Hartanto

Used 2+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

1 min • 1 pt

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed. Which two actions should the project manager take? (Choose 2)
Ask the customer for their priorities regarding the requirements for the second milestone
Convince the customer to leave the second milestone in place and not change it
Tell the customer that moving the milestone has a very high impact on the cost of the project
Go back to the development team and discuss which second milestone requirements can be performed in the first quarter
Escalate the issue to upper management to resolve the problem

2.

MULTIPLE SELECT QUESTION

1 min • 1 pt

The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration. Which three techniques should the project manager use? (Choose 3)
Iterations and reviews to continuously keep adapting the plan
Gantt chart that includes milestones and deadlines
Rolling wave planning and an adaptive approach
Bottom-up estimating based on a work breakdown structure (WBS)
Relative estimation to determine the task or deliverable sizes

3.

MULTIPLE SELECT QUESTION

1 min • 1 pt

A project manager for a large, multiyear, industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement. Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose 2)
Communications management plan
Ishikawa diagrams
Open-space meetings
Issue log
Five whys

4.

MULTIPLE SELECT QUESTION

1 min • 1 pt

A project manager has been assigned to an education project with the objective of training a workforce in application development. One of the deliverables is to provide internships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decides to create several internal projects in order to ensure the internships. Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)
Influence the client to initiate a new project
Create a change request with the scope of the new internal projects
Use the project's contingency budget
Manage the quality of the delivery
Create a work breakdown structure (WBS) of the new scope with the internal projects

5.

MULTIPLE SELECT QUESTION

1 min • 1 pt

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose 3)
Adjust the project management plan to include the changes in scope
Continue the execution as planned and defer the changes to a future phase
Highlight the impacts of the changes during the next project meeting
Schedule a meeting with the customer to align the approach
Update the relevant project documents with this obstacle