Quiz Lesson 3 - Topic D (Resources and Procurement)

Quiz
•
Professional Development
•
Professional Development
•
Medium
Abdul Habib Aulfat
Used 4+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of the RACI chart in resource management?
To define procurement phases for acquiring resources
To allocate budget resources to specific tasks
To clarify roles and responsibilities for project activities
To determine competency gaps in the project team
Answer explanation
The primary purpose of the RACI chart is to clarify roles and responsibilities for project activities, ensuring that everyone understands their specific contributions and accountability within the project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What document describes how goods and services will be procured in a project?
Statement of Work (SOW)
Procurement Management Plan
Resource Management Plan
Request for Proposal (RFP)
Answer explanation
The Procurement Management Plan outlines how goods and services will be acquired for a project, detailing procurement processes, roles, and responsibilities, making it the correct choice.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which procurement document is used to gather basic information about potential sellers?
Invitation for Bid (IFB)
Request for Information (RFI)
Request for Proposal (RFP)
Request for Quotation (RFQ)
Answer explanation
The Request for Information (RFI) is specifically designed to gather basic information about potential sellers, helping organizations understand the market and capabilities before proceeding with further procurement steps.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following best describes a cost-plus-fixed-fee (CPFF) contract?
The seller is paid a fixed amount regardless of project costs.
The seller is reimbursed for actual costs plus a fixed fee.
The seller is paid a fixed price with incentives for performance.
The seller is reimbursed for costs and awarded an additional fee for exceptional work.
Answer explanation
A cost-plus-fixed-fee (CPFF) contract means the seller is reimbursed for actual costs incurred plus a fixed fee for their services, making the second option the correct description.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In adaptive teams, why are team members encouraged to be T-shaped?
It ensures every team member has deep expertise in one area.
It allows team members to take on both specialist and generalist roles.
It enforces strict hierarchy and responsibilities in the team.
It ensures every team member works only on their primary responsibility.
Answer explanation
In adaptive teams, being T-shaped means team members can specialize in one area while also having the flexibility to contribute in other areas. This versatility enhances collaboration and problem-solving.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of a resource calendar in project management?
To track project deliverables and timelines
To identify the working days and availability of resources
To allocate financial resources to specific activities
To document team roles and responsibilities
Answer explanation
The resource calendar is essential for identifying the working days and availability of resources, ensuring effective scheduling and resource allocation throughout the project.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a key difference in resource management between predictive and adaptive approaches?
Adaptive approaches use hierarchical teams, while predictive does not.
Predictive approaches assign resources based on detailed upfront planning, while adaptive teams self-organize to distribute work.
Predictive approaches rely solely on generalists, while adaptive approaches use specialists.
Adaptive teams follow strict resource allocation plans.
Answer explanation
The key difference is that predictive approaches rely on detailed upfront planning for resource allocation, while adaptive teams self-organize, allowing for more flexibility in distributing work.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Quiz Lesson 3 - Topic G (Quality)

Quiz
•
Professional Development
15 questions
SG20_Test_S8_CH10&13 Communications & Stakeholder

Quiz
•
Professional Development
8 questions
Quiz Lesson 3 - Topic H (Integrate Plans)

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
5 questions
Work Breakdown Structure - Assignment

Quiz
•
Professional Development
14 questions
Agility Basics

Quiz
•
Professional Development
12 questions
Bid and Tender Management

Quiz
•
Professional Development
10 questions
Procurement 10 soal (Chapter 12)

Quiz
•
Professional Development
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade