Quiz Lesson 3 - Topic F (Risks)

Quiz Lesson 3 - Topic F (Risks)

Professional Development

10 Qs

quiz-placeholder

Similar activities

UNICEF

UNICEF

Professional Development

6 Qs

Project management principles

Project management principles

Professional Development

12 Qs

PROJECT MANAGINNG RISKS

PROJECT MANAGINNG RISKS

University - Professional Development

10 Qs

Risk 10 soal (Chapter 11)

Risk 10 soal (Chapter 11)

Professional Development

10 Qs

Quizz Risk Management

Quizz Risk Management

Professional Development

10 Qs

Risk & Opportunity Management  PRE-TEST

Risk & Opportunity Management PRE-TEST

Professional Development

15 Qs

Risk Management

Risk Management

University - Professional Development

10 Qs

DG Quiz

DG Quiz

Professional Development

14 Qs

Quiz Lesson 3 - Topic F (Risks)

Quiz Lesson 3 - Topic F (Risks)

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Abdul Habib Aulfat

Used 6+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a trigger condition represent in risk management?

A risk that occurs due to external factors

A situation indicating that a risk event is about to happen

The level of risk appetite acceptable to the organization

A mitigation strategy to address a known risk

Answer explanation

A trigger condition in risk management indicates a situation where a risk event is likely to occur, allowing organizations to prepare and respond proactively.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is an example of a business risk in project management?

A risk that could lead to regulatory noncompliance

A competitive risk that could lead to either profit or loss

A resource-related issue affecting project performance

A project schedule overrun due to poor estimation

Answer explanation

A competitive risk that could lead to either profit or loss directly impacts a business's financial performance, making it a significant business risk in project management compared to other options.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which risk response strategy involves transferring ownership of a threat to a third party?

Escalate

Avoid

Transfer

Mitigate

Answer explanation

The correct answer is 'Transfer' because this risk response strategy involves shifting the responsibility of a threat to a third party, such as through insurance or outsourcing.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a risk register?

To track project compliance with legal requirements

To document identified risks and their management plans

To determine organizational risk appetite and threshold

To calculate expected monetary value (EMV)

Answer explanation

The primary purpose of a risk register is to document identified risks and their management plans, ensuring that risks are tracked and addressed effectively throughout the project lifecycle.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the difference between a secondary risk and a residual risk?

Secondary risks occur due to poor planning; residual risks occur after project closure.

Secondary risks arise from implementing risk responses, while residual risks remain after implementing responses.

Secondary risks are external to the project, while residual risks are internal.

Secondary risks are addressed in contingency planning, while residual risks are escalated.

Answer explanation

Secondary risks arise from the actions taken to mitigate primary risks, while residual risks are the remaining risks that persist after all risk responses have been implemented.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a valid opportunity response strategy?

Mitigate

Share

Transfer

Avoid

Answer explanation

The valid opportunity response strategy among the options is 'Share'. This strategy involves distributing the risk or opportunity among multiple parties, which is a recognized approach in risk management.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a probability and impact matrix help project managers achieve?

Assign ownership to risks

Rank risks based on their likelihood and potential effect on project objectives

Identify secondary risks and their mitigation strategies

Calculate expected monetary value (EMV) for all risks

Answer explanation

A probability and impact matrix helps project managers rank risks based on their likelihood and potential effect on project objectives, allowing for better prioritization and management of risks.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?