Quiz Lesson 4 - Topic G (Manage Conflict)

Quiz Lesson 4 - Topic G (Manage Conflict)

Professional Development

7 Qs

quiz-placeholder

Similar activities

Conflict Management

Conflict Management

Professional Development

12 Qs

Resource Mgmt Pre-test

Resource Mgmt Pre-test

Professional Development

10 Qs

Conflict Management

Conflict Management

Professional Development

10 Qs

Guess conflict management

Guess conflict management

Professional Development

3 Qs

Project Closure

Project Closure

Professional Development

10 Qs

Conflict Management & Resolution

Conflict Management & Resolution

Professional Development

11 Qs

LifeSkills - Batch 4 - Compensation Quiz

LifeSkills - Batch 4 - Compensation Quiz

Professional Development

11 Qs

Engagement & Conflict

Engagement & Conflict

Professional Development

8 Qs

Quiz Lesson 4 - Topic G (Manage Conflict)

Quiz Lesson 4 - Topic G (Manage Conflict)

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Abdul Habib Aulfat

Used 7+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager notices a disagreement between two team members regarding the project's technical approach. To address this, the project manager arranges a meeting where both parties can discuss their viewpoints and collaboratively develop a solution. Which conflict resolution technique is being utilized?

Forcing

Compromising

Collaborating

Avoiding

Answer explanation

The project manager is facilitating a meeting for both team members to discuss and find a solution together, which exemplifies the collaborating technique. This approach aims for a win-win outcome by integrating their viewpoints.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project meeting, a team member consistently interrupts others, leading to frustration among the team. The project manager decides to have a private conversation with the individual to address the behavior. Which conflict resolution strategy is being applied?

Smoothing

Forcing

Avoiding

Confronting

Answer explanation

The project manager is addressing the individual's interruptive behavior directly, which is a form of confrontation. This strategy aims to resolve the issue by discussing it openly, making 'Confronting' the correct choice.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Two departments are in conflict over resource allocation. The project manager decides to split the resources equally between them, even though it may not be the optimal solution for either. Which conflict resolution method is this?

Compromising

Collaborating

Forcing

Avoiding

Answer explanation

The project manager's decision to split resources equally reflects a compromising approach, where both departments receive a portion of what they want, even if it's not ideal for either side.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager decides to temporarily set aside a conflict between two team members, hoping it will resolve itself over time. Which conflict resolution strategy is this?

Smoothing

Avoiding

Forcing

Collaborating

Answer explanation

The project manager is choosing to avoid the conflict rather than addressing it directly. This strategy is known as avoiding, as it involves setting aside the issue in hopes it resolves itself.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a heated discussion, a project manager decides to agree with a stakeholder's viewpoint to maintain harmony, even though they have reservations. Which conflict resolution technique is being used?

Forcing

Compromising

Smoothing

Avoiding

Answer explanation

The project manager is using the smoothing technique by agreeing with the stakeholder to maintain harmony, despite having reservations. This approach prioritizes relationship over the issue at hand.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager enforces a decision to resolve a conflict between team members without seeking their input, believing it's in the project's best interest. Which conflict resolution method is this?

Collaborating

Forcing

Compromising

Smoothing

Answer explanation

The project manager's unilateral decision to resolve the conflict without team input exemplifies the 'Forcing' method, where one party imposes a solution, prioritizing their perspective over collaboration.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a conflict over project priorities, the project manager encourages open communication and facilitates a discussion to understand all perspectives, aiming for a solution that satisfies everyone. Which conflict resolution strategy is being employed?

Avoiding

Compromising

Collaborating

Forcing

Answer explanation

The project manager's approach of encouraging open communication and understanding all perspectives reflects the collaborating strategy, which seeks a win-win solution that satisfies everyone involved.