Quiz Lesson 5 - Topic D (Manage Project Issues and Impediments)

Quiz Lesson 5 - Topic D (Manage Project Issues and Impediments)

Professional Development

8 Qs

quiz-placeholder

Similar activities

Soft Skills in the work place

Soft Skills in the work place

Professional Development

10 Qs

Drilling Quiz W-2/II

Drilling Quiz W-2/II

Professional Development

10 Qs

Project Management

Project Management

Professional Development

10 Qs

Agile Communication - Assignment

Agile Communication - Assignment

Professional Development

7 Qs

SA Scrum Master 6.0 L1

SA Scrum Master 6.0 L1

Professional Development

11 Qs

Drilling W2-Nov 2021

Drilling W2-Nov 2021

Professional Development

10 Qs

PSM Quiz 4

PSM Quiz 4

Professional Development

10 Qs

Agile Mindset Quiz

Agile Mindset Quiz

Professional Development

12 Qs

Quiz Lesson 5 - Topic D (Manage Project Issues and Impediments)

Quiz Lesson 5 - Topic D (Manage Project Issues and Impediments)

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Abdul Habib Aulfat

Used 2+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary role of a Scrum Master regarding impediments?

To delegate the removal of impediments to team members

To remove impediments and facilitate consensus

To ignore impediments that are minor

To document impediments without taking action

Answer explanation

The primary role of a Scrum Master is to remove impediments that hinder the team's progress and to facilitate consensus among team members, ensuring a smooth workflow and effective collaboration.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes an 'issue' in project management?

An uncertain event that might impact the project in the future

A current condition negatively affecting the project

A minor inconvenience that does not require documentation

An external event with no impact on the project

Answer explanation

An 'issue' in project management refers to a current condition negatively affecting the project, distinguishing it from uncertainties or minor inconveniences that do not impact the project's progress.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In project management, what distinguishes a 'risk' from an 'issue'?

A risk is a potential future problem; an issue is a current problem

A risk has a positive impact; an issue has a negative impact

A risk can be ignored; an issue cannot be ignored

There is no difference between a risk and an issue

Answer explanation

A risk refers to a potential problem that may occur in the future, while an issue is a problem that is currently affecting the project. This distinction is crucial for effective project management.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should a project manager handle an issue that exceeds set thresholds?

Ignore the issue until it resolves on its own

Escalate the issue to the project sponsor or appropriate stakeholder

Document the issue and wait for a team meeting

Assign the issue to an external consultant

Answer explanation

When an issue exceeds set thresholds, the project manager should escalate it to the project sponsor or appropriate stakeholder. This ensures that the issue is addressed promptly and effectively, rather than ignored or delayed.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of an impediment log in Agile project management?

To track the completion dates of all project tasks

To record and manage obstacles affecting the team

To log the personal issues of team members

To document approved project changes

Answer explanation

The impediment log is essential in Agile project management as it records and manages obstacles affecting the team, ensuring that issues are addressed promptly to maintain project progress.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which action is critical when managing blockers in a project environment?

Reducing the frequency of team meetings

Increasing the project budget arbitrarily

Prioritizing critical blockers for resolution

Ignoring blockers that seem trivial

Answer explanation

Prioritizing critical blockers for resolution is essential in project management. It ensures that the most significant issues are addressed first, preventing delays and keeping the project on track.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When should a project manager re-assess the handling of impediments, obstacles, and blockers?

Annually

Never

At the end of the project

Continually

Answer explanation

A project manager should re-assess impediments, obstacles, and blockers continually to ensure the project remains on track. This proactive approach allows for timely resolution and adaptation to changing circumstances.

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key strategy for solving problems in a Scrum environment?

Avoiding discussion of problems in daily meetings

Using network to implement solutions

Solving problems without team input

Focusing solely on local optimization

Answer explanation

In a Scrum environment, leveraging the network to implement solutions fosters collaboration and collective problem-solving, which is essential for team success. The other options hinder teamwork and effective communication.