Quiz Lesson 6 - Topic A (Project/Phase Closure)

Quiz Lesson 6 - Topic A (Project/Phase Closure)

Professional Development

8 Qs

quiz-placeholder

Similar activities

P&T Agile 101 Quiz

P&T Agile 101 Quiz

Professional Development

8 Qs

Project Closure

Project Closure

Professional Development

10 Qs

Quiz Lesson 6 - Topic B (Benefits Realization)

Quiz Lesson 6 - Topic B (Benefits Realization)

Professional Development

8 Qs

Project Scope

Project Scope

Professional Development

7 Qs

SG20_Test_S4_CH5 Scope

SG20_Test_S4_CH5 Scope

Professional Development

10 Qs

RDL1-Agile Testing

RDL1-Agile Testing

Professional Development

12 Qs

Drilling Quiz W-2/II

Drilling Quiz W-2/II

Professional Development

10 Qs

Resource Mgmt Pre-test

Resource Mgmt Pre-test

Professional Development

10 Qs

Quiz Lesson 6 - Topic A (Project/Phase Closure)

Quiz Lesson 6 - Topic A (Project/Phase Closure)

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Abdul Habib Aulfat

Used 4+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of assessing the readiness of all parties involved in a project change?

To determine the project budget

To ensure successful adoption and overcome resistance

To allocate more resources to the project

To prolong the project timeline

Answer explanation

The primary purpose of assessing readiness is to ensure successful adoption of the change and to overcome any resistance from stakeholders, which is crucial for the project's overall success.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of these is not typically included as a change request type?

Corrective action

Preventive action

Budget increase request

Defect repair

Answer explanation

A budget increase request is not a change request type; it pertains to funding rather than project scope or quality changes. Corrective actions, preventive actions, and defect repairs are all related to managing project deliverables.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What role does the Change Control Board (CCB) play in project management?

Designs project deliverables

Approves project funding

Reviews and approves changes to the project

Manages the project team directly

Answer explanation

The Change Control Board (CCB) is responsible for reviewing and approving changes to the project, ensuring that any modifications align with project goals and do not negatively impact the project's scope, timeline, or budget.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the 'Definition of Done' (DoD) used for in Agile project management?

To describe the project scope fully

To indicate when a deliverable is ready for customer use

To finalize the project budget

To negotiate project contracts

Answer explanation

The 'Definition of Done' (DoD) is a checklist that indicates when a deliverable meets all criteria and is ready for customer use, ensuring quality and completeness before release.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement best describes the importance of transition plans in project management?

They are optional documents that teams can ignore.

They outline how deliverables are handed to the customer.

They are used to increase project costs.

They primarily function to hire new team members.

Answer explanation

Transition plans are crucial as they detail how deliverables are transferred to the customer, ensuring clarity and smooth handover, which is essential for project success.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key activity during the closure or transition phase of a project?

Beginning new projects

Expanding the project scope

Validating readiness for transition

Reducing project resources prematurely

Answer explanation

Validating readiness for transition is crucial during the closure phase to ensure that all project deliverables meet requirements and stakeholders are prepared for the next steps, making it the key activity.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should a project manager handle the archival of contracts?

Disregard any documentation.

Collect, index, and file essential documents like the contract schedule and change documentation.

Archive only digital copies.

Store documents without indexing.

Answer explanation

A project manager should collect, index, and file essential documents like the contract schedule and change documentation to ensure proper organization and easy retrieval, making this the best practice for contract archival.

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be included in the transition requirements of a project?

Reducing communication with the project team

Avoiding any training on new products or services

Documentation and training on the new product or service

Immediate project termination after delivery

Answer explanation

Transition requirements should include documentation and training on the new product or service to ensure users are well-prepared and can effectively utilize the new offerings, making this the correct choice.