Week 8 - EVM

Week 8 - EVM

University

5 Qs

quiz-placeholder

Similar activities

Quiz Manajemen Proyek Perangkat Lunak

Quiz Manajemen Proyek Perangkat Lunak

University

5 Qs

Multiple Choice Quiz: Designing for Impact

Multiple Choice Quiz: Designing for Impact

University

10 Qs

SOFTWARE ENGINEERING

SOFTWARE ENGINEERING

University

10 Qs

Экзамин

Экзамин

University

10 Qs

Quiz on Project Management and Information Technology

Quiz on Project Management and Information Technology

University

10 Qs

MongoDB Concepts 2

MongoDB Concepts 2

University

10 Qs

Software Engineering - Unit 2 Quiz(Challenging)

Software Engineering - Unit 2 Quiz(Challenging)

University

5 Qs

Software Development Processes Quiz

Software Development Processes Quiz

University

7 Qs

Week 8 - EVM

Week 8 - EVM

Assessment

Quiz

Created by

Taiwo Adedeji

Information Technology (IT)

University

2 plays

Medium

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has an EV of £2.25k and an AC of £2.5k. What does the resulting CV indicate about the project's cost?

The project is under budget

The project is on budget

The project is over budget

The cost status cannot be determined

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a project’s SPI is calculated as 75%, which scenario best describes its schedule performance?

The project is behind schedule

The project is ahead of schedule

The project is on schedule

The project schedule cannot be assessed

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During an app development project, AC is £3.25k, PV is £3k, and EV is £2.75k. What does SPI reveal about delivery?

The project is progressing faster than planned

The project is behind schedule

Delivery is on track

Delivery progress is unknown

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A team uses EVM but fails to establish a baseline before tracking progress. Which essential EVM data dependency is missing?

Actual cost

Earned value

Planned value

Schedule variance

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How would using EVM in Agile project management most likely differ from traditional settings?

EVM cannot coexist with Agile practices

Agile requires continuous re-baselining for effective EVM

Agile only tracks profit margins, not EVM metrics

EVM implementation in Agile is fully automated and simple