
PMP - Scope
Authored by Nguyễn Đạt
Education
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A work breakdown structure numbering system allows the project team to:
Answer explanation
The numbering system allows team members to quickly identify the level in the work breakdown structure where the specific element is found. It also helps to locate the element in the WBS dictionary
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The work breakdown structure can BEST be thought of as an effective aid for _________ communications.
Answer explanation
The term "stakeholder" encompasses all the other choices. In this case, it is the best answer since the WBS can be used (but does not need to be used) as a communications tool for all stakeholders to "see" what is included in the project
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is a KEY output of the Verify Scope process?
Answer explanation
The output of the Verify Scope process is customer acceptance of project deliverables. The other choices all happen during project planning, well before the time the Verify Scope process takes place
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?
Answer explanation
Activity lists may identify the work package they relate to, but they do not contain detailed descriptions of the work packages. The project scope statement defines the project scope, but it does not describe the work a team member is assigned. The scope management plan describes how scope will be planned, managed, and controlled. It does not include a description of each work package. The WBS dictionary defines each element in the WBS
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During which part of the project management process is the project scope statement created?
Answer explanation
The project scope statement is an output of the Define Scope process, which occurs during project planning
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The program was planned years ago, before there was a massive introduction of new technology. While planning the next project in this program, the project manager has expanded the scope management plan because, as a project becomes more complex, the level of uncertainty in the scope:
Answer explanation
The level of uncertainty in scope increases based on the scale of effort required to identify all the scope. For larger projects, it is more difficult to "catch" everything
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:
Answer explanation
Though one could let the sponsor know about the stakeholders' request, the best choice listed would be to say no. An even better choice would be to find the root cause of the problem, but that choice is not listed here
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?