PMP - Scope

PMP - Scope

University

30 Qs

quiz-placeholder

Similar activities

LEADERSHIP AND MOTIVATION

LEADERSHIP AND MOTIVATION

University

25 Qs

Project Management - Evaluation

Project Management - Evaluation

University

30 Qs

TM 1 - MANAJEMEN PROYEK IT

TM 1 - MANAJEMEN PROYEK IT

University

30 Qs

HEROES LEADERS QUIZ BEE

HEROES LEADERS QUIZ BEE

University

30 Qs

ETECH

ETECH

12th Grade - University

26 Qs

HEROES LEADERS QUIZ BEE

HEROES LEADERS QUIZ BEE

University

30 Qs

principle of management chapter 1

principle of management chapter 1

University

30 Qs

PMP - Scope

PMP - Scope

Assessment

Quiz

Education

University

Hard

Created by

Nguyễn Đạt

Used 1+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A work breakdown structure numbering system allows the project team to:
Systematically estimate costs of work breakdown structure elements
Provide project justification
Identify the level at which individual elements are found
Use it in project management software

Answer explanation

The numbering system allows team members to quickly identify the level in the work breakdown structure where the specific element is found. It also helps to locate the element in the WBS dictionary

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The work breakdown structure can BEST be thought of as an effective aid for _________ communications.
Team
Project manager
Customer
Stakeholder

Answer explanation

The term "stakeholder" encompasses all the other choices. In this case, it is the best answer since the WBS can be used (but does not need to be used) as a communications tool for all stakeholders to "see" what is included in the project

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is a KEY output of the Verify Scope process?
A more complete scope management plan
Customer acceptance of project deliverables
Improved schedule estimates
An improved project management information system

Answer explanation

The output of the Verify Scope process is customer acceptance of project deliverables. The other choices all happen during project planning, well before the time the Verify Scope process takes place

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?
WBS dictionary
Activity list
Project scope statement
Scope management plan

Answer explanation

Activity lists may identify the work package they relate to, but they do not contain detailed descriptions of the work packages. The project scope statement defines the project scope, but it does not describe the work a team member is assigned. The scope management plan describes how scope will be planned, managed, and controlled. It does not include a description of each work package. The WBS dictionary defines each element in the WBS

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During which part of the project management process is the project scope statement created?
Initiating
Planning
Executing
Monitoring and controlling

Answer explanation

The project scope statement is an output of the Define Scope process, which occurs during project planning

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The program was planned years ago, before there was a massive introduction of new technology. While planning the next project in this program, the project manager has expanded the scope management plan because, as a project becomes more complex, the level of uncertainty in the scope:
Remains the same
Decreases
Decreases then increases
Increases

Answer explanation

The level of uncertainty in scope increases based on the scale of effort required to identify all the scope. For larger projects, it is more difficult to "catch" everything

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:
Let the sponsor know of the stakeholders' request
Evaluate the impact of adding the scope
Tell the stakeholders the scope cannot be added
Add the work if there is time available in the project schedule

Answer explanation

Though one could let the sponsor know about the stakeholders' request, the best choice listed would be to say no. An even better choice would be to find the root cause of the problem, but that choice is not listed here

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?