
Construction Contract - Delay & EOT
Quiz
•
Construction
•
University
•
Practice Problem
•
Medium
FARRAH A
Used 2+ times
FREE Resource
Enhance your content in a minute
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary responsibility of the contractor after being given possession of the site?
To renegotiate the contract terms
To commence work at their discretion
To proceed regularly and diligently to complete the work by the stipulated Completion Date
To avoid all potential disputes with the employer
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does "Employer Delay" typically refer to?
Delays caused by subcontractors
Delays resulting from the contractor's inefficiencies
Delays caused by the acts or omissions of the employer or architect
Delays due to exceptionally inclement weather
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which clause in the PAM Contract deals with the submission of notice and particulars for an extension of time (EOT)?
Clause 23.4
Clause 23.8
Clause 23.1
Clause 23.6
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to Clause 23.1, what must the contractor include in their notice for an EOT?
The contractor's anticipated profit margins
All subcontractor performance records
Initial estimate of EOT required, cause of the delay, and relevant particulars
The architect's anticipated completion timeline
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is classified as a "Neutral Event" under Clause 23.8?
Acts of prevention by the employer
Exceptionally inclement weather
Negligence by subcontractors
Delayed payment by the employer
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Under Clause 23.8, which event does NOT qualify for EOT?
Discovery of antiquities
Force majeure
Delays due to contractor negligence
Civil commotion
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does Clause 23.6 require the contractor to do?
Constantly use their best endeavours to prevent or reduce delay
Transfer liability for delays to the architect
Ignore delays caused by the employer
Terminate the contract in case of significant delays
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
0 questions
Contract Admin week 2
Quiz
•
0 questions
Contract Breach Quiz
Quiz
•
0 questions
CMA 385 - Exam 2 Review - Chapters: 4 & 5
Quiz
•
0 questions
Construction Terms
Quiz
•
0 questions
Construction Management
Quiz
•
0 questions
Certificate of Maintenance Review Quiz
Quiz
•
0 questions
Contract Changes Quiz
Quiz
•
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Construction
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
20 questions
christmas songs
Quiz
•
KG - University
20 questions
Holiday Trivia
Quiz
•
9th Grade - University
15 questions
Holiday Movies
Quiz
•
University
14 questions
Christmas Trivia
Quiz
•
3rd Grade - University
20 questions
Christmas Trivia
Quiz
•
University
8 questions
5th, Unit 4, Lesson 8
Lesson
•
KG - Professional Dev...
20 questions
Disney Trivia
Quiz
•
University
