Construction Contract - Delay & EOT

Construction Contract - Delay & EOT

University

20 Qs

quiz-placeholder

Similar activities

305 Cold water systems 3 Quiz

305 Cold water systems 3 Quiz

2nd Grade - University

18 Qs

SMAW Equipment and Supplies

SMAW Equipment and Supplies

10th Grade - University

15 Qs

Cordless Drill Identification of Components #2

Cordless Drill Identification of Components #2

11th Grade - University

15 Qs

Intro to Drafting

Intro to Drafting

University

15 Qs

Chapter 7 contracts

Chapter 7 contracts

University

17 Qs

306 hot water systems 2 Quiz

306 hot water systems 2 Quiz

2nd Grade - University

20 Qs

ALTERNATIVE DISPUTES RESOLUTION

ALTERNATIVE DISPUTES RESOLUTION

University

23 Qs

Belt and Disc Sander - Safety procedure Quiz

Belt and Disc Sander - Safety procedure Quiz

7th Grade - University

20 Qs

Construction Contract - Delay & EOT

Construction Contract - Delay & EOT

Assessment

Quiz

Construction

University

Medium

Created by

FARRAH A

Used 2+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary responsibility of the contractor after being given possession of the site?

To renegotiate the contract terms

To commence work at their discretion

To proceed regularly and diligently to complete the work by the stipulated Completion Date

To avoid all potential disputes with the employer

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does "Employer Delay" typically refer to?

Delays caused by subcontractors

Delays resulting from the contractor's inefficiencies

Delays caused by the acts or omissions of the employer or architect

Delays due to exceptionally inclement weather

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which clause in the PAM Contract deals with the submission of notice and particulars for an extension of time (EOT)?

Clause 23.4

Clause 23.8

Clause 23.1

Clause 23.6

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to Clause 23.1, what must the contractor include in their notice for an EOT?

The contractor's anticipated profit margins

All subcontractor performance records

Initial estimate of EOT required, cause of the delay, and relevant particulars

The architect's anticipated completion timeline

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is classified as a "Neutral Event" under Clause 23.8?

Acts of prevention by the employer

Exceptionally inclement weather

Negligence by subcontractors

Delayed payment by the employer

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Under Clause 23.8, which event does NOT qualify for EOT?

Discovery of antiquities

Force majeure

Delays due to contractor negligence

Civil commotion

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does Clause 23.6 require the contractor to do?

Constantly use their best endeavours to prevent or reduce delay

Transfer liability for delays to the architect

Ignore delays caused by the employer

Terminate the contract in case of significant delays

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?