Waterfall mindset 2 New

Waterfall mindset 2 New

1st Grade

10 Qs

quiz-placeholder

Similar activities

Content Resource Site Quizzz

Content Resource Site Quizzz

KG - University

10 Qs

Awareness Assessment (Elementary level)

Awareness Assessment (Elementary level)

1st Grade

10 Qs

STORING SANDWICH

STORING SANDWICH

1st Grade

11 Qs

Fortnite

Fortnite

1st Grade

6 Qs

Code of Ethics for Teachers

Code of Ethics for Teachers

KG - Professional Development

10 Qs

Virtual Technology for the 21st Century Educators

Virtual Technology for the 21st Century Educators

1st - 10th Grade

10 Qs

Desarrollo de Aplicaciones Modernas y Herramientas.

Desarrollo de Aplicaciones Modernas y Herramientas.

1st Grade - Professional Development

15 Qs

HELLO FM III STUDENTS

HELLO FM III STUDENTS

1st - 10th Grade

10 Qs

Waterfall mindset 2 New

Waterfall mindset 2 New

Assessment

Quiz

Professional Development

1st Grade

Practice Problem

Easy

Created by

Afghanistan Center

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are managing a project nearing its completion. One of your team members suggests focusing only on critical tasks to meet the final deadline. However, you notice that the project's lessons learned repository has not been updated since the project began. What should you do?

Complete the critical tasks first and address lessons learned after project closure.

Allocate time now to update lessons learned even if it impacts the schedule.

Let the project team update the lessons learned repository after the final deliverable.

Capture only key lessons and summarize them in the final project report.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the project closure phase, you discover that a few supplier invoices are still pending payment. What is your next step?

Close the project and inform finance to handle the pending payments.

Ensure all pending invoices are paid before closing the project.

Request an exception from the sponsor to close the project.

Prioritize final deliverable acceptance over payment settlement.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team member reports an issue during the final stages of your project. They suggest resolving it immediately without documenting it to avoid delays. What is the best action?

Resolve the issue without documentation to avoid unnecessary complexity.

Document the issue and work with the team to resolve it promptly.

Assign the issue to a task force and let them handle documentation later.

Defer the issue to the operational team post-project closure.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have inherited a struggling project. To deliver it successfully, you must resolve conflicts between different teams and ensure alignment with the overall project goals. What should you focus on?

Act as an integrator to align team efforts and resolve conflicts.

Escalate conflicts to the project sponsor for resolution.

Prioritize technical execution over alignment activities.

Delay resolution until a formal risk review can be conducted.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your team has completed the final deliverables, and you are in the process of closing the project. A stakeholder reminds you that some issues encountered during execution were never addressed. What should you do?

Ignore unresolved issues as the project deliverables are complete.

Ensure all issues are documented and included in the closure report.

Confirm with stakeholders that the issues are no longer relevant.

Note unresolved issues in a future risk log for other projects.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A critical supplier informs you that they cannot deliver materials for the next project phase. This impacts the project schedule and budget. How should you approach this situation?

Work to integrate the supplier’s constraints into the revised project plan.

Escalate the issue to the project sponsor immediately.

Terminate the supplier and find an alternative source.

Continue with the project plan as-is and manage risks later.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing the project documentation during closure, you notice that the lessons learned document contains minimal input. What should you do?

Proceed with project closure and address lessons learned in the next project.

Schedule a lessons learned meeting to gather insights from the team.

Submit the document as-is to meet the deadline.

Encourage team members to submit their lessons individually post-closure.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?