Prince 2 Foundation Quiz

Prince 2 Foundation Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

CRMP - Practice Module 1-7

CRMP - Practice Module 1-7

Professional Development

10 Qs

Team Development Stages - Assignment

Team Development Stages - Assignment

Professional Development

5 Qs

Bid and Tender Management

Bid and Tender Management

Professional Development

12 Qs

Project Integration Management

Project Integration Management

Professional Development

15 Qs

Procurement and tendering

Procurement and tendering

Professional Development

10 Qs

Contributing to the delivery of a project

Contributing to the delivery of a project

Professional Development

12 Qs

GRIP

GRIP

Professional Development

8 Qs

Project Management Methodologies - Assigment

Project Management Methodologies - Assigment

Professional Development

8 Qs

Prince 2 Foundation Quiz

Prince 2 Foundation Quiz

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

PMI Trainer

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

PRINCE2 mandates that the project board represents the primary stakeholder interests.

Which principle does this follow?

Manage by stages

Focus on products

Define roles and responsibilities and relationships

Learn from experience

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is change management important in a project?

Because stakeholders should understand which organizational areas are impacted by the project

Because the project products should be described and subject to change control

Because confidence is needed that the project can meet its objectives and continues to be justified

Because user’s quality expectations of the project products should be understood

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which practice establishes mechanisms to monitor and compare actual achievements against those planned?

Progress

Plans

Issues

Quality

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is a purpose of the business case practice?

To establish mechanisms for managing issues that may impact the baseline

To establish methods to judge whether the ongoing project is justified

To assess and control uncertain

  events or situations

To describe how products will be                    delivered that are fit for purpose

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement describes the directing a project process?

It enables the project board to assure that there is continued business justification

It covers the day-to-day activities of the project manager

It ensures that there are regular progress meetings

It begins on completion of the

  initiating a project process

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What takes place during the closing a project process?

The post-project benefits reviews are performed

Ownership of the project's products is transferred to the customer

An end stage report is prepared for the final stage

The project closure notification is reviewed and approved

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is an objective of the managing a stage boundary process?

To request authorization to start the next stage

To ensure that all threats and opportunities for the current stage have been closed

To ensure that work on products allocated to the team for the next stage is authorized

To implement actions to resolve tolerance deviations from the stage plan

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?