
300-401 N

Quiz
•
Mathematics
•
1st Grade
•
Hard
Afghanistan Center
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?
Accommodate the change request to serve the client's needs
Consult with team members and allow them to make a decision
Convince the client not to make changes to the project
Make transactional decisions focusing on the project goals
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows. What should the project manager have done?
Conveyed task completion information to accounting
Closed the procurement process properly
Completed the transition process
Performed administrative closure of the project
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A large company has agreed on a business case for an environmental project. The project will cause some major changes in their operations, such as reduction in paper use, which will obviously affect all of the users. What is the first thing the appointed project manager should do?
Evaluate the impact to the users and create a plan to address it.
Inform users about the new changes and ask for their collaboration.
Ask all managers to collaborate implementing this change to users.
Start implementing the change so that users will eventually get used to it.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain. What should the project manager do?
Plan for incremental and iterative delivery based on feedback from the marketing and sales team.
Review and update the success criteria to ensure that the channel is not decommissioned.
Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.
Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team requests a change in the sprint goals and sprint backlog items. What should the project manager do?
Create a parallel sprint to deliver the additional items.
Guide the agile team to add the new scope to the product backlog.
Pause the sprint to allow time to include the new items.
Moderate the expectations for sprint quality.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project. What should the project manager do next?
Update the assumptions log and change log, and implement the change control process.
Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.
Inform the client that the project cannot meet the project timeline and additional costs will be incurred.
Deliver what was planned in the project management document according to the specifications.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule. What should the project manager do?
Ensure that relevant stakeholders and expectations are identified and assess the component delay.
Perform a detailed analysis of the release content for each component of the solution.
Propose a new design of the solution to replace the external component with an internal one.
Ask for expedited delivery of the component to mitigate the risk of schedule delays.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Introduction to Machine Learning

Quiz
•
KG - Professional Dev...
15 questions
Are You Smarter Than A Fifth Grader (CH eddition)

Quiz
•
1st - 5th Grade
6 questions
Exercise 3m Fractions

Quiz
•
1st Grade
15 questions
MATHEMATICS FOR ALL

Quiz
•
1st - 5th Grade
10 questions
super heoros

Quiz
•
1st - 8th Grade
11 questions
Jackie Robinson: A Story of Bravery and Change

Quiz
•
1st Grade
10 questions
Grade 1 Mathematics Quiz - Division

Quiz
•
1st Grade
15 questions
IQ Quiz 1

Quiz
•
1st Grade - Professio...
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
10 questions
Afterschool Activities & Sports

Quiz
•
6th - 8th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
15 questions
Cool Tool:Chromebook

Quiz
•
6th - 8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
20 questions
Bullying

Quiz
•
7th Grade
18 questions
7SS - 30a - Budgeting

Quiz
•
6th - 8th Grade
Discover more resources for Mathematics
20 questions
addition

Quiz
•
1st - 3rd Grade
20 questions
Addition and Subtraction facts

Quiz
•
1st - 3rd Grade
20 questions
Number Words Challenge

Quiz
•
1st - 5th Grade
20 questions
Place Value

Quiz
•
KG - 3rd Grade
10 questions
Basic Addition

Quiz
•
1st Grade
22 questions
Addition and Subtraction Facts

Quiz
•
1st - 2nd Grade
29 questions
Addition

Quiz
•
1st - 3rd Grade
10 questions
Exploring the States of Matter: Solid, Liquid, and Gas

Interactive video
•
1st - 5th Grade