In the poker planning session, the following stow points were given to a particular user story
<p>
Product owner: 3
Developers: 5
Testers: 8
<p>
Which action should the team agree on?
ISTQB Agile Tester Extension Exam Crash Course Part 4
Quiz
•
Science
•
Professional Development
•
Easy
Hiếu Bồ
Used 7+ times
FREE Resource
40 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the poker planning session, the following stow points were given to a particular user story
<p>
Product owner: 3
Developers: 5
Testers: 8
<p>
Which action should the team agree on?
Answer explanation
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a Planning Poker session the team is estimating the effort for User story 1 and User story 2 which are related to the same feature.
<p>
The team has agreed on the story points for user story 1 but In the discussion of user story 2, the tester realized that he is not aware of the additional information about the business rules and external interfaces which may increase the testing effort for user story 1.
<p>
What should the tester do in this situation?
Answer explanation
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
One of the Agile Teams are doing the estimation for the following user story:
<p>
“As an online Shopper, I want to delete items from my shopping cart so that I don’t purchase items that I decide I don’t want”
<p>
The tester has asked the following questions to the product owner to get a better understanding of the functionality for estimation purposes.
<p>
Which of the tester’s question is not relevant for the estimation process?
Answer explanation
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In agile projects there is more need for testers to understand and develop test automation scripts than in traditional projects.
<p>
Of the following, which are the TWO reasons why this is a necessary skill on agile projects?
<p>
i. Requirements change daily and have to be regression tested. This rapid change requires automated tests because manual testing is too slow.
ii. The tests should generate feedback on product quality as early as possible. So all acceptance tests should be executed during each iteration, ideally as modifications are made. In practice that can only be realized by automated tests.
iii. Test-First and Continuous Integration practice require that the regression test suite is executed whenever changed code is checked-in. In practice that can only be realized by automated tests.
iv. Iterations or sprints are of fixed length. The team has to guarantee that all tests can be completely executed at the last day of each iteration/sprint. In practice, that can only be realized by automated tests.
v. Agile projects rely on unit testing rather than on systems testing. Since unit tests cannot be executed manually, all tests have to be automated tests.
Answer explanation
Statement (ii) & (iii) best describe the conditions for agile projects.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Agile team is assigned to a project to create a mobile interface for an existing web-based application.
<p>
A few of the features are not supported in the mobile interface and the way a user can access the interface is also changing and will be documented in user stories. Based on this information, and in addition to the user stories, Out of the following which would best provide relevant information to support your testing activities?
<p>
i. Existing functions, features, and quality characteristics of the web-based application
ii. Architecture diagrams for the web-based application.
iii. Obsolete user access test cases for the web-based application.
iv. Performance metrics for existing application.
v. Defects from existing and previous releases of the web-based application.
Answer explanation
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Agile team is building a new system, to replace a legacy system, to efficiently store customer information using a new relational database. For the testing of this new system, out of the following which would best provide relevant information to support testing activities In addition to the user stories?
<p>
i. Experience in testing the legacy system.
ii. Performance metrics from the legacy system.
iii. Architecture diagrams of the legacy system.
iv. Customer profiles from the legacy system.
v. Defects list from the legacy system.
Answer explanation
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Agile team is working on a project for a new payment application. Out of the following which would best provide relevant information to support testing activities In addition to the user stories for the testing of new payment messages from the payer to the payee?
<p>
i. Updated standard documents for existing payment applications.
ii. Information about the data schema and how the data is stored in database
iii. Architecture diagrams for the new payment application.
iv. Performance metrics for a similar payment application.
v. Defects from an existing payment applications.
Answer explanation
40 questions
ISTQB Foundation 2
Quiz
•
Professional Development
40 questions
ISTQB Foundation 10
Quiz
•
Professional Development
40 questions
ISTQB Question Bank 261 to 300
Quiz
•
Professional Development
40 questions
ISTQB - Mobile Application Testing 03
Quiz
•
Professional Development
40 questions
ISTQB Agile Tester Extension Exam Crash Course Part 1
Quiz
•
Professional Development
40 questions
Agile Tester Foundation Sample Exam 003
Quiz
•
Professional Development
40 questions
ISTQB Question Bank 501 to 540
Quiz
•
Professional Development
40 questions
ISTQB Question Bank 181 to 220
Quiz
•
Professional Development
15 questions
Character Analysis
Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing
Quiz
•
9th - 12th Grade
10 questions
American Flag
Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension
Quiz
•
5th Grade
30 questions
Linear Inequalities
Quiz
•
9th - 12th Grade
20 questions
Types of Credit
Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25
Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers
Quiz
•
6th - 8th Grade