Waterfall mindset 1-2

Waterfall mindset 1-2

9th Grade

10 Qs

quiz-placeholder

Similar activities

GFAH Quiz...

GFAH Quiz...

1st - 10th Grade

10 Qs

LET IV Leadership Accomplishments

LET IV Leadership Accomplishments

9th - 12th Grade

15 Qs

Conflict Resolution

Conflict Resolution

9th - 12th Grade

10 Qs

SolidWorks - conceitos I

SolidWorks - conceitos I

1st - 11th Grade

11 Qs

Project Data

Project Data

3rd Grade - University

10 Qs

Learner-centred approaches

Learner-centred approaches

KG - Professional Development

10 Qs

Construct 2 Basics

Construct 2 Basics

2nd Grade - Professional Development

10 Qs

Workforce Vocabulary

Workforce Vocabulary

1st - 12th Grade

13 Qs

Waterfall mindset 1-2

Waterfall mindset 1-2

Assessment

Quiz

Professional Development

9th Grade

Easy

Created by

Afghanistan Center

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager discovers a new stakeholder halfway through the project who has a significant influence on the project outcome. What should the project manager do?

Ignore the stakeholder as they were not identified during the initiation phase.

Analyze the stakeholder's influence and include them in the stakeholder engagement plan.

Inform the stakeholder that changes to the project plan cannot be made at this stage.

Delegate stakeholder management to a team member.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team member identifies a potential risk that could disrupt the project schedule. They suggest making an immediate change to the project plan to address it. What should the project manager do?

Allow the team member to implement the change immediately.

Submit a change request for review and approval before modifying the plan.

Reject the suggestion as the plan should not be altered once approved.

Update the plan based on the team member’s suggestion without further analysis.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the execution phase, a senior stakeholder requests additional deliverables. What is the best course of action for the project manager?

Include the additional deliverables as per the stakeholder’s request.

Inform the stakeholder that changes are not possible once execution has begun.

Submit a formal change request for review and assessment.

Reassign resources to accommodate the additional deliverables.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project sponsor asks the project manager to start procurement activities immediately due to time constraints. However, the project’s procurement plan has not been developed. How should the project manager respond?

Begin procurement activities as requested to avoid delays.

Refuse to proceed until a procurement plan is created and approved.

Delegate the responsibility to a senior team member to expedite the process.

Procure only the essential items and develop the plan later.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a conflict between two stakeholders about project requirements, the project manager considers making a decision independently to avoid further delays. What is the best approach?

Make the decision independently to resolve the conflict quickly.

Consult with the project team for practical insights before making a decision.

Postpone the decision until stakeholders resolve their conflict.

Implement both stakeholders’ requirements to avoid further disputes.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager is conducting a workshop with stakeholders to prioritize requirements. What tool should the project manager use to ensure inclusivity?

A sophisticated project management software for prioritization.

A simple whiteboard and markers to facilitate open discussion.

A detailed spreadsheet shared online for remote inputs.

A voting application that only a few stakeholders are familiar with.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new stakeholder group emerges that has conflicting priorities with the original stakeholder group. What should the project manager do?

Focus only on the original stakeholder group as they were identified at the start.

Reassess the new stakeholder group and update the stakeholder engagement plan.

Ignore the new stakeholder group as it might derail the project’s progress.

Hold a meeting with the original group to address potential conflicts.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?