
Waterfall mindset 6
Quiz
•
Professional Development
•
4th Grade
•
Medium
Afghanistan Center
Used 5+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a final inspection of a new product, the quality team discovers a critical defect that could impact customer satisfaction. The project manager must take immediate action. What should the project manager do?
Conduct a quality investigation and initiate corrective actions.
Use the contingency reserve to cover the cost of additional testing.
Meet with the client to explain the cause of the defect.
Send the client a letter apologizing for the issue.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a progress meeting, the project team learns about an emerging risk that could cause major delays. The project manager realizes that the risk was not documented in the risk register. What should the project manager do next?
Ask the project sponsor to apply the management reserve to cover the impact of the risk.
Ask the project sponsor to provide additional contingency funds.
Issue a change request to modify the scope, cost, and schedule accordingly.
Use the contingency reserve and assess options for risk response.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team working in an adaptive approach is facing delays due to unforeseen risks. The project manager wants to ensure that risks are identified as early as possible and documented properly. During a risk review meeting, a team member suggests using daily stand-up meetings to capture new risks. What should the project manager do?
Use the call to verbally summarize the work status and move forward.
Use an electronic task board to give a visual representation of risks and mitigation actions.
Ask for a change in the project's budget to provide additional funding for risk resolution.
Tailor the project to use a method to make the risk identification process more formal.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In order to reduce procurement time during a bidding process, a project manager is evaluating different contracting approaches. The objective is to select a contract that ensures fairness for both the buyer and the seller. What should the project manager do?
Invite all potential bidders to a meeting.
Award the contract without negotiation.
Follow the company's bidding procedure.
Share the project objectives with all bidders.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution of repair work, the root cause of the problem is found to be a defect in materials provided by the seller. The contract was fixed-price with no provisions for cost-sharing on defects. The seller refuses to cover the costs of repair, citing contract terms. What should the project manager do?
Negotiate with the contractor to cancel the repair work.
Negotiate the repair work with the contractor and explore cost-sharing options.
Proceed with the contractor without mentioning the defect.
Proceed with the contractor and subtract the additional repair cost from the seller’s payment.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A key stakeholder frequently misses project status meetings, making it difficult for the project manager to communicate critical updates. What should the project manager do?
Continue sending meeting invitations and assume the stakeholder will join eventually.
Schedule one-on-one discussions with the stakeholder to understand their concerns.
Escalate the issue to the project sponsor and request a stakeholder replacement.
Assign another team member to communicate with the stakeholder.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project involves multiple stakeholders from different departments, and the project manager is struggling to ensure effective communication. Some stakeholders prefer detailed reports, while others prefer high-level summaries. What should the project manager do?
Send the same detailed report to all stakeholders to ensure consistency.
Provide customized communication formats based on stakeholder preferences.
Schedule mandatory in-person meetings for all stakeholders.
Default to email communication to ensure documentation.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
7 questions
Taxes Quiz
Quiz
•
3rd - 7th Grade
10 questions
Bi Weekly DMAIC - DEFINE
Quiz
•
1st - 10th Grade
13 questions
TEACHING PROFESSION
Quiz
•
1st - 10th Grade
12 questions
We Keep Our Hands, Feet and Objects to Ourselves
Quiz
•
2nd - 6th Grade
11 questions
Design thinking 2020
Quiz
•
1st - 5th Grade
15 questions
agencje reklamowe
Quiz
•
1st - 5th Grade
14 questions
G Suite - The Basics
Quiz
•
KG - 12th Grade
15 questions
Accommodations and Modifications
Quiz
•
KG - University
Popular Resources on Wayground
20 questions
Halloween Trivia
Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Order of Operations
Quiz
•
5th Grade
20 questions
Halloween
Quiz
•
5th Grade
16 questions
Halloween
Quiz
•
3rd Grade
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
20 questions
Possessive Nouns
Quiz
•
5th Grade
10 questions
Halloween Traditions and Origins
Interactive video
•
5th - 10th Grade
Discover more resources for Professional Development
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
15 questions
Subject-Verb Agreement
Quiz
•
4th Grade
21 questions
Factors and Multiples
Quiz
•
4th Grade
13 questions
Point of View
Quiz
•
4th Grade
20 questions
Theme
Quiz
•
4th Grade
14 questions
Halloween Fun
Quiz
•
2nd - 12th Grade
15 questions
Halloween Fun
Quiz
•
3rd - 5th Grade
20 questions
Prepositions and prepositional phrases
Quiz
•
4th Grade
