Waterfall mindset 6

Waterfall mindset 6

4th Grade

10 Qs

quiz-placeholder

Similar activities

Risk Response Strategies - Negative Risks

Risk Response Strategies - Negative Risks

4th Grade

6 Qs

PMGT Week 5 - PMBOK Ch 13

PMGT Week 5 - PMBOK Ch 13

KG - University

11 Qs

Roles of PMO in Organization

Roles of PMO in Organization

4th Grade

5 Qs

PMP 2017 PEOPLE

PMP 2017 PEOPLE

1st - 12th Grade

10 Qs

CBAP Prep Quiz 1

CBAP Prep Quiz 1

1st - 5th Grade

14 Qs

Quality Vs. Grade

Quality Vs. Grade

4th Grade

7 Qs

Project Management Methodologies

Project Management Methodologies

4th Grade

8 Qs

Risk Response Strategies - Positive Risks

Risk Response Strategies - Positive Risks

4th Grade

7 Qs

Waterfall mindset 6

Waterfall mindset 6

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 5+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a final inspection of a new product, the quality team discovers a critical defect that could impact customer satisfaction. The project manager must take immediate action. What should the project manager do?

Conduct a quality investigation and initiate corrective actions.

Use the contingency reserve to cover the cost of additional testing.

Meet with the client to explain the cause of the defect.

Send the client a letter apologizing for the issue.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a progress meeting, the project team learns about an emerging risk that could cause major delays. The project manager realizes that the risk was not documented in the risk register. What should the project manager do next?

Ask the project sponsor to apply the management reserve to cover the impact of the risk.

Ask the project sponsor to provide additional contingency funds.

Issue a change request to modify the scope, cost, and schedule accordingly.

Use the contingency reserve and assess options for risk response.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team working in an adaptive approach is facing delays due to unforeseen risks. The project manager wants to ensure that risks are identified as early as possible and documented properly. During a risk review meeting, a team member suggests using daily stand-up meetings to capture new risks. What should the project manager do?

Use the call to verbally summarize the work status and move forward.

Use an electronic task board to give a visual representation of risks and mitigation actions.

Ask for a change in the project's budget to provide additional funding for risk resolution.

Tailor the project to use a method to make the risk identification process more formal.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to reduce procurement time during a bidding process, a project manager is evaluating different contracting approaches. The objective is to select a contract that ensures fairness for both the buyer and the seller. What should the project manager do?

Invite all potential bidders to a meeting.

Award the contract without negotiation.

Follow the company's bidding procedure.

Share the project objectives with all bidders.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the execution of repair work, the root cause of the problem is found to be a defect in materials provided by the seller. The contract was fixed-price with no provisions for cost-sharing on defects. The seller refuses to cover the costs of repair, citing contract terms. What should the project manager do?

Negotiate with the contractor to cancel the repair work.

Negotiate the repair work with the contractor and explore cost-sharing options.

Proceed with the contractor without mentioning the defect.

Proceed with the contractor and subtract the additional repair cost from the seller’s payment.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A key stakeholder frequently misses project status meetings, making it difficult for the project manager to communicate critical updates. What should the project manager do?

Continue sending meeting invitations and assume the stakeholder will join eventually.

Schedule one-on-one discussions with the stakeholder to understand their concerns.

Escalate the issue to the project sponsor and request a stakeholder replacement.

Assign another team member to communicate with the stakeholder.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project involves multiple stakeholders from different departments, and the project manager is struggling to ensure effective communication. Some stakeholders prefer detailed reports, while others prefer high-level summaries. What should the project manager do?

Send the same detailed report to all stakeholders to ensure consistency.

Provide customized communication formats based on stakeholder preferences.

Schedule mandatory in-person meetings for all stakeholders.

Default to email communication to ensure documentation.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?