Risk, Documents, Specifications, EIA

Risk, Documents, Specifications, EIA

University

10 Qs

quiz-placeholder

Similar activities

Atividade segunda unidade

Atividade segunda unidade

11th Grade - University

10 Qs

Terminología Básica

Terminología Básica

University

10 Qs

[WEEK 9] LET'S SQUEEZE THE QUIZ

[WEEK 9] LET'S SQUEEZE THE QUIZ

University

10 Qs

Tutorial 1

Tutorial 1

University

15 Qs

Copa Airlines Quiz

Copa Airlines Quiz

University

10 Qs

Vocabulary List #Mar2

Vocabulary List #Mar2

12th Grade - University

10 Qs

Blue Print Lines

Blue Print Lines

University

13 Qs

Civil-Day1

Civil-Day1

University

14 Qs

Risk, Documents, Specifications, EIA

Risk, Documents, Specifications, EIA

Assessment

Quiz

Construction

University

Medium

Created by

Emma Coyle

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Project Execution Plan (PEP) outlines:

How a project will be executed and controlled

The total project cost

The final approval from the government

The business case analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many steps are there in the risk management process?

1

2

3

4

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Risk Avoidance is one risk response we can take on a project. Which one of these is an example of risk avoidance?

Buying insurance

Changing the design to prevent this risk occurring

Accepting the risk as part of the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Subcontracting an element of work is a method of risk transfer..

True

False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a project risk register?

A financial spreadsheet that tracks project expenses and cost overruns.

A schedule that lists project tasks and deadlines.

A document that records identified risks, their impact, likelihood, and mitigation strategies

A legal document required for obtaining planning permission.

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The factors considered for analysing and prioritising project risks are :

Probability

Cost

Severity

Quality

Resources

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Under the Construction Regulations 2013, a Designer’s Risk Assessment should

Exclude safety concerns

Only focus on financial risk

Be completed after construction starts

Identify H&S risks associated with the construction, operation, maintenance and decommissioning of the building.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?