Estimating 2

Estimating 2

University

10 Qs

quiz-placeholder

Similar activities

PRELIMINARY ESTIMATING METHOD

PRELIMINARY ESTIMATING METHOD

University

15 Qs

Accounting Concept

Accounting Concept

University

10 Qs

cost accounting

cost accounting

University

11 Qs

Mixed  Arki SPP No.2

Mixed Arki SPP No.2

University

15 Qs

Time management

Time management

6th Grade - University

12 Qs

CST 241 Ch 1 In class quiz

CST 241 Ch 1 In class quiz

University

10 Qs

CMA I - Joint & By-Product

CMA I - Joint & By-Product

University

10 Qs

Estimating is fun

Estimating is fun

University

15 Qs

Estimating 2

Estimating 2

Assessment

Quiz

Other

University

Hard

Created by

NOOR (POLIKK)

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a preliminary cost estimate?

To determine the final project cost

To forecast the probable construction cost before the detailed design

To negotiate contractor payments

To determine profit margins

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following factors influence a cost estimate?

Type, shape, and size of the building

Quality of materials used

Methods of construction

All of the above

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a consequence of an excessively low preliminary cost estimate?

The design could be inferior

The project cost remains unchanged

The client receives excess funds

The construction is completed faster

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a method of preliminary cost estimation?

Floor area method

Storey enclosure method

Approximate quantities method

Net profit method

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Unit Method of preliminary cost estimation, how is the cost estimated?

Based on the total gross floor area

By multiplying the cost per unit of accommodation by the number of units

Using elemental cost planning

By evaluating composite work items

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method is commonly used in Malaysia to estimate the cost of air-conditioned spaces?

Floor Area Method

Cubic Method

Storey Enclosure Method

Elemental Estimate

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a key disadvantage of the Floor Area Method?

It does not consider differences in building height and shape

It is too complex for clients to understand

It cannot be used for public sector projects

It is the slowest method to obtain cost estimates

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?