07 Test - CPM, estimating, resources

07 Test - CPM, estimating, resources

University

26 Qs

quiz-placeholder

Similar activities

star wars

star wars

5th Grade - Professional Development

21 Qs

LIS126 Prelim Exam

LIS126 Prelim Exam

University

21 Qs

Call of duty quiz

Call of duty quiz

4th Grade - University

21 Qs

On my block

On my block

1st Grade - Professional Development

21 Qs

untitled

untitled

6th Grade - University

22 Qs

Fiber Optic Assignment  Quiz

Fiber Optic Assignment Quiz

University

22 Qs

Endocrine Exam 3-Khan

Endocrine Exam 3-Khan

University

22 Qs

UAE Switch Gathering

UAE Switch Gathering

1st Grade - Professional Development

21 Qs

07 Test - CPM, estimating, resources

07 Test - CPM, estimating, resources

Assessment

Quiz

Other

University

Practice Problem

Hard

Created by

Jurgita Raščiuvienė

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

26 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not true for the critical path?

It has zero float.

It ’ s the shortest activity sequence in the network.

You can determine which tasks can start late without impacting the project end date.

It controls the project finish date.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?

There is a mandatory dependency between Activity A and Activity B.

There is a finish - to - start dependency relationship between Activity A and Activity B.

Activity A and Activity B are both on the critical path.

Activity B is a successor to multiple tasks.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is true for float or slack time?

It ’ s calculated by adding the durations of all activities and dividing by the number of activities.

It ’ s time that you add to the project schedule to provide a buffer or contingency.

It’s the amount of time an activity can be delayed without delaying the project completion.

It is only calculated on the longest path of the network diagram.

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which of the following is not a tool used to determine a project ’ s critical path?

Forward pass

Mandatory dependency

Float calculation

Backward pass

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate of 11 days, and an optimistic estimate of 6 days. What is the three - point estimate for this task rounded to the nearest whole number?

11 days

25 days

8 days

6 days

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not true for critical path activities?

The early start is always less than the late start.

These activities are on the longest path on the network diagram.

The float is zero.

The late finish is always the same as the early finish.

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You are estimating a new project with team. Team members say the project is very similar to the previous one that they worked. They can list all pitfalls. Based on their experience in the previous project they can prepare the estimate very quickly. What estimation technique the team is using?

Expert judgment

Analogous estimating

PERT

Algorithmic technique function based

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?