
07 Test - CPM, estimating, resources
Quiz
•
Other
•
University
•
Practice Problem
•
Hard
Jurgita Raščiuvienė
Used 4+ times
FREE Resource
Enhance your content in a minute
26 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not true for the critical path?
It has zero float.
It ’ s the shortest activity sequence in the network.
You can determine which tasks can start late without impacting the project end date.
It controls the project finish date.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?
There is a mandatory dependency between Activity A and Activity B.
There is a finish - to - start dependency relationship between Activity A and Activity B.
Activity A and Activity B are both on the critical path.
Activity B is a successor to multiple tasks.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following is true for float or slack time?
It ’ s calculated by adding the durations of all activities and dividing by the number of activities.
It ’ s time that you add to the project schedule to provide a buffer or contingency.
It’s the amount of time an activity can be delayed without delaying the project completion.
It is only calculated on the longest path of the network diagram.
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Which of the following is not a tool used to determine a project ’ s critical path?
Forward pass
Mandatory dependency
Float calculation
Backward pass
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate of 11 days, and an optimistic estimate of 6 days. What is the three - point estimate for this task rounded to the nearest whole number?
11 days
25 days
8 days
6 days
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not true for critical path activities?
The early start is always less than the late start.
These activities are on the longest path on the network diagram.
The float is zero.
The late finish is always the same as the early finish.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
You are estimating a new project with team. Team members say the project is very similar to the previous one that they worked. They can list all pitfalls. Based on their experience in the previous project they can prepare the estimate very quickly. What estimation technique the team is using?
Expert judgment
Analogous estimating
PERT
Algorithmic technique function based
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
23 questions
International contracts
Quiz
•
University
23 questions
MCND quiz
Quiz
•
1st Grade - Professio...
24 questions
The Sacrament of Confirmation
Quiz
•
9th Grade - University
21 questions
rebel vs conformist
Quiz
•
6th Grade - University
21 questions
padam
Quiz
•
University
22 questions
untitled
Quiz
•
9th Grade - University
22 questions
Chapter 5: Thickening agent, Soup, Stocks and Sauces
Quiz
•
University
23 questions
Introduction of V9i
Quiz
•
University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Other
7 questions
How James Brown Invented Funk
Interactive video
•
10th Grade - University
5 questions
Helping Build the Internet: Valerie Thomas | Great Minds
Interactive video
•
11th Grade - University
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
23 questions
Subject Verb Agreement
Quiz
•
9th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
19 questions
Review2-TEACHER
Quiz
•
University
15 questions
Pre2_STUDENT
Quiz
•
University
20 questions
Ch. 7 Quadrilateral Quiz Review
Quiz
•
KG - University
