Quiz 2 Training Project Management [15/04/25]

Quiz 2 Training Project Management [15/04/25]

Professional Development

5 Qs

quiz-placeholder

Similar activities

Product  Discovery

Product Discovery

Professional Development

9 Qs

RTES

RTES

Professional Development

10 Qs

CCPM PHR WK Rokan

CCPM PHR WK Rokan

Professional Development

10 Qs

Building Construction Quiz

Building Construction Quiz

Professional Development

9 Qs

Power Automate Quiz

Power Automate Quiz

Professional Development

10 Qs

TIMING TEST

TIMING TEST

Professional Development

10 Qs

Sosialisasi IMS dan PR402.6 TIF SBS

Sosialisasi IMS dan PR402.6 TIF SBS

Professional Development

10 Qs

FMEA Day 1 of 3

FMEA Day 1 of 3

Professional Development

10 Qs

Quiz 2 Training Project Management [15/04/25]

Quiz 2 Training Project Management [15/04/25]

Assessment

Quiz

Engineering

Professional Development

Hard

Created by

Bella Fadli

Used 5+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

If a project does not align anymore with the benefits then the project should be stopped. This principle is known as?

Project Context

Ensure Business Justification

Manage by Stages

Sustainability

2.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE2 to a project.

Which role should be accountable for approving these

proposals?

Project board

Project manager

Project assurance

Business layer

3.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

Which term is defined as the means by which an organization

transitions from its current state to the target state?

Change management

Change control

Progress management

Risk management

4.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

The project board needs to confirm that there is enough information to initiate the project. What should the project board review?

Business case

Benefits management approach

Project brief

Project plan

5.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

Which is a purpose of the ‘plans’ practice?

To provide the standards against which the project products can be

quality controlled

To enable an event that requires project management consideration to

be controlled

To enable control of opportunities and threats, that could impact on

delivery of the business objectives

To provide the basis of control against which a project’s progress can be monitored