Scrum Ceremonies - Assignment

Scrum Ceremonies - Assignment

Professional Development

7 Qs

quiz-placeholder

Similar activities

SCRUM

SCRUM

Professional Development

6 Qs

Agile Product/ Project Management Quiz

Agile Product/ Project Management Quiz

Professional Development

12 Qs

Agile Management SCRUM Concept 01

Agile Management SCRUM Concept 01

Professional Development

10 Qs

Agile course - Week 3 challenges

Agile course - Week 3 challenges

Professional Development

10 Qs

Advance Scrum Master Academy- Day 3

Advance Scrum Master Academy- Day 3

Professional Development

10 Qs

Eventos-Anti-Patrones

Eventos-Anti-Patrones

Professional Development

12 Qs

Influencer Quiz

Influencer Quiz

Professional Development

10 Qs

Assesment

Assesment

Professional Development

10 Qs

Scrum Ceremonies - Assignment

Scrum Ceremonies - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

Used 1+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kunar province, the Scrum Team gathers at the beginning of the sprint to decide which Product Backlog items they will complete and how they will achieve the work.Which Scrum ceremony is taking place?

Daily Scrum

Sprint Planning

Sprint Retrospective

Sprint Review

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Takhar province, each morning, the Scrum Team meets for 15 minutes to discuss what was done yesterday, what will be done today, and any blockers they are facing.What Scrum ceremony is this?

Sprint Planning

Daily Scrum

Sprint Review

Backlog Refinement

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Baghlan province, at the end of the sprint, the Scrum Team demonstrates the new functionality they developed to key stakeholders and collects feedback.Which Scrum ceremony is happening?

Sprint Retrospective

Sprint Planning

Sprint Review

Daily Scrum

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Khost province, after completing a sprint, the Scrum Team meets privately to discuss what went well, what didn’t, and how they can improve processes for the next sprint.What Scrum ceremony is being conducted?

Sprint Review

Sprint Retrospective

Daily Scrum

Sprint Planning

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kyoto city in Japan, a Scrum Team continuously updates, adds, and clarifies Product Backlog items throughout the sprint to keep the work prioritized and ready for upcoming sprints.Which Scrum activity are they engaged in?

Sprint Review

Backlog Refinement

Daily Scrum

Sprint Planning

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Faryab province, the Product Owner, Scrum Master, and Development Team collaborate to set a clear Sprint Goal before pulling backlog items into the Sprint Backlog.Which Scrum event is this?

Daily Scrum

Sprint Planning

Sprint Retrospective

Sprint Review

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Bogotá city in Colombia, after delivering a set of new app features, the team invites end users to review the deliverables and suggest any adjustments or new priorities.Which Scrum ceremony does this represent?

Sprint Retrospective

Sprint Review

Daily Scrum

Backlog Refinement