Manage Knowledge Management - Assignment

Manage Knowledge Management - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

Final Quiz - Assignment

Final Quiz - Assignment

Professional Development

10 Qs

EEF_OPA - Assignment

EEF_OPA - Assignment

Professional Development

8 Qs

Resource - Final Quiz - Assignment

Resource - Final Quiz - Assignment

Professional Development

9 Qs

Prevention VS Correction - Assignment

Prevention VS Correction - Assignment

Professional Development

7 Qs

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT

Professional Development

10 Qs

Quiz Lesson 5 - Topic E (Manage Project Changes)

Quiz Lesson 5 - Topic E (Manage Project Changes)

Professional Development

8 Qs

Deloitte- Position Vs Interest- Meaningful Conversations

Deloitte- Position Vs Interest- Meaningful Conversations

Professional Development

10 Qs

Quiz for Become A Project Manager

Quiz for Become A Project Manager

Professional Development

10 Qs

Manage Knowledge Management - Assignment

Manage Knowledge Management - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Faryab province, a project engineer writes a detailed user manual explaining the procedures for operating newly installed medical equipment. What type of knowledge is being captured?

Tacit Knowledge

Explicit Knowledge

Expert Judgment

Organizational Process Assets

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Zabul province, a senior project manager shares tips based on personal experience about how to build trust with difficult stakeholders during a mentoring session. What type of knowledge is being transferred?

Tacit Knowledge

Explicit Knowledge

Quality Metrics

Procurement Knowledge

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Badghis province, after completing a community development project, the team records lessons learned regarding best practices and challenges faced during implementation. Which process does this activity support?

Managing Communications

Managing Project Knowledge

Monitoring Risks

Validating Scope

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kathmandu city in Nepal, the Scrum Team uploads retrospective reports, templates, and technical checklists into the organizational knowledge base after each sprint. Which output are they creating?

Issue Log

Lessons Learned Register

Stakeholder Register

Scope Management Plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Panjshir province, a new team member joins a project and accesses an archive of past project reports to better understand risk management practices. Which benefit of Manage Project Knowledge is being utilized?

Creating new baselines

Reusing organizational knowledge to improve project performance

Identifying new stakeholders

Validating Scope Deliverables