Perform Integrated Change Control - Assignment

Perform Integrated Change Control - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

Quiz Lesson 3 - Topic A (Planning Projects)

Quiz Lesson 3 - Topic A (Planning Projects)

Professional Development

8 Qs

Schedule Management Processes - Assignment

Schedule Management Processes - Assignment

Professional Development

6 Qs

Project Management (Week 4)

Project Management (Week 4)

Professional Development

8 Qs

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT

Professional Development

10 Qs

EEF_OPA - Assignment

EEF_OPA - Assignment

Professional Development

8 Qs

Final Quiz - Assignment

Final Quiz - Assignment

Professional Development

10 Qs

Quiz for Become A Project Manager

Quiz for Become A Project Manager

Professional Development

10 Qs

Quiz Lesson 5 - Topic E (Manage Project Changes)

Quiz Lesson 5 - Topic E (Manage Project Changes)

Professional Development

8 Qs

Perform Integrated Change Control - Assignment

Perform Integrated Change Control - Assignment

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Afghanistan Center

Used 1+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Takhar province, the project team submits a change request to add new features to a training program after getting feedback from stakeholders.Which process is responsible for reviewing, approving, or rejecting the change request?

Monitor and Control Project Work

Perform Integrated Change Control

Direct and Manage Project Work

Plan Scope Management

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Badakhshan province, during the execution phase, a customer requests changes to the product features.What should the project manager do first according to the Perform Integrated Change Control process?

Immediately incorporate the changes into the scope

Evaluate the change for impact on scope, schedule, and cost

Close the project phase early

Create a risk register update

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Jawzjan province, the project team collects and documents all change requests and sends them to the Change Control Board (CCB) for decision-making.What role is the CCB performing?

Quality Assurance

Risk Analysis

Change Evaluation and Approval

Contract Administration

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kathmandu city in Nepal, after a scope change is approved, the project manager updates the project management plan and communicates the changes to all stakeholders.What activity is happening?

Recording Lessons Learned

Managing Communications

Updating Documents and Communicating Approved Changes

Controlling Quality

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Laghman province, a project sponsor asks the project manager about the final decision on a proposed budget change request.Which document typically records the outcomes of change requests?

Risk Register

Change Log

Communications Management Plan

Quality Metrics