Instrumentation – Chapter 18 – Test Bank

Instrumentation – Chapter 18 – Test Bank

Professional Development

6 Qs

quiz-placeholder

Similar activities

FMEA Day 1 of 3

FMEA Day 1 of 3

Professional Development

10 Qs

Configuring the Timeline Control and Creating Card Forms

Configuring the Timeline Control and Creating Card Forms

Professional Development

10 Qs

Modal verbs

Modal verbs

Professional Development

10 Qs

Quiz on Security Patches and Updates

Quiz on Security Patches and Updates

Professional Development

6 Qs

Introduction to Garment Production

Introduction to Garment Production

Professional Development

7 Qs

Review materi

Review materi

Professional Development

10 Qs

Basic Structure of a PLC

Basic Structure of a PLC

Professional Development

7 Qs

Intro to Carbon Footprint Assessment

Intro to Carbon Footprint Assessment

Professional Development

7 Qs

Instrumentation – Chapter 18 – Test Bank

Instrumentation – Chapter 18 – Test Bank

Assessment

Quiz

Engineering

Professional Development

Hard

Created by

Scott SANDVIK

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a conditional logic in which a process is either fully engaged or not engaged at all?

Boolean logic

And/or

If/then

On/off

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to have accurate PLC ladder drawings?

Technicians did not have the training to modify diagrams.

Modifications were time-consuming.

To avoid injury.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What do PLCs allow?

Changes to the shelf position to be recorded automatically

Changes to MCCs to be recorded automatically

Changes to DCS to be recorded automatically

Changes to ladder diagrams to be recorded automatically

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is and/or logic used to control?

A process in which either one or both variables exist

A process so that the process is either fully engaged or not engaged at all

A process in which multiple conditions are present at once

A process in which one condition leads to the next

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following rely heavily on PLCs?

Washing machines

Car horns

Air conditioners

Emergency shutdown systems

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the most commonly used method for interfacing with a PLC?

Function block diagrams

Structured text

Ladder diagrams

Instruction list