1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of Presidential Decree No. 1594?
To set guidelines for private contracts
To manage tourism infrastructure
To regulate foreign investments
To prescribe policies for government infrastructure contracts
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Before a project is awarded, what must be completed?
Environmental clearance
Public consultation
Detailed engineering
Right-of-way acquisition
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What type of contractor qualification involves experience and available equipment?
Legal
Technical
Financial
Administrative
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which method is primarily used for undertaking construction projects under PD 1594?
Negotiated Contract
Force Account
Public Bidding
Administration
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the minimum retention money required during progress payments?
5%
10%
15%
20%
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What must accompany the bid to ensure contract compliance?
Payment receipt
Bidders bond
Contractor license
Notice to proceed
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is responsible for project inspection under PD 1594?
The contractor
The local government
The private consultant
The government agency
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?