Before the team in Uruzgan province creates the project schedule, they agree on scheduling tools, reporting frequency, and how performance will be tracked.Which process is being executed?
Schedule Final Quiz - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Define Activities
Plan Schedule Management
Control Schedule
Planning framework setup involving tool alignment, stakeholder dashboards, and scheduling baselines
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While preparing for construction in Daykundi province, the team breaks the high-level deliverable “Build clinic” into smaller tasks such as digging, plumbing, and tiling. What process are they carrying out?
Develop Schedule
Estimate Activity Durations
Define Activities
Subtask planning with task deconstruction, effort assignment, and resource pooling
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an effort to build logical task flow in Ghazni province, the coordinator arranges activities based on dependencies, ensuring proper task order and timing. Which process is being followed?
Develop Schedule
Estimate Activity Durations
Sequence Activities
Task logic alignment using relationship modeling and sequence buffering
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After receiving input from engineers in Laghman province, the project manager calculates that each solar panel installation will take four days based on historical data. Which process does this reflect?
Estimate Activity Durations
Define Activities
Control Schedule
Effort forecasting through resource review and benchmarked productivity metrics
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Using MS Project in Berlin, the team inputs task durations and dependencies, then analyzes the Gantt chart and critical path to set a realistic timeline. What process are they completing?
Develop Schedule
Control Schedule
Sequence Activities
Time modeling through logic-driven schedule creation with float and path visibility
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While reviewing actual progress against the plan in Balkh province, the manager notices that key activities are behind schedule and considers adding weekend work to catch up. What process is this?
Develop Schedule
Control Schedule
Define Activities
Reactive scheduling review using baseline comparison and corrective action evaluation
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, a documentation task is allowed to start two days before coding is complete, to accelerate delivery without waiting for 100% task finish. Which scheduling technique is being used?
Lag
Crashing
Lead
Task concurrency model with forecast-based overlap and priority realignment
Similar Resources on Quizizz
7 questions
Subsidery Plan - Assignment

Quiz
•
Professional Development
7 questions
Prevention VS Correction - Assignment

Quiz
•
Professional Development
5 questions
Estimating Techniques - Assignment

Quiz
•
Professional Development
10 questions
Inclusive Scheduling Quiz

Quiz
•
Professional Development
7 questions
Schedule Management Terms - Assignment

Quiz
•
Professional Development
10 questions
NodeJs: Cron jobs

Quiz
•
Professional Development
7 questions
Conflict Resolution Techniques - Assignment

Quiz
•
Professional Development
7 questions
Integration Process - Assignment

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade