Schedule Final Quiz - Assignment

Schedule Final Quiz - Assignment

Professional Development

7 Qs

quiz-placeholder

Similar activities

TIME MANAGEMENT PRE TEST

TIME MANAGEMENT PRE TEST

8th Grade - Professional Development

12 Qs

Practice Exam 2 Part 3

Practice Exam 2 Part 3

Professional Development

10 Qs

12082022 KS SCHEDULING STRATEGY FOR DYNAMIC ENVIRONMENT DIGITAL

12082022 KS SCHEDULING STRATEGY FOR DYNAMIC ENVIRONMENT DIGITAL

Professional Development

10 Qs

Quiz Lesson 3 - Topic C (Schedule)

Quiz Lesson 3 - Topic C (Schedule)

Professional Development

10 Qs

Project Management Master Class 3

Project Management Master Class 3

Professional Development

10 Qs

Quizziz 3- Knowledge Area 3 and 5

Quizziz 3- Knowledge Area 3 and 5

Professional Development

10 Qs

i-OPTIMIZE 2019

i-OPTIMIZE 2019

Professional Development

10 Qs

Curriculum Night! 2021-2022

Curriculum Night! 2021-2022

Professional Development

12 Qs

Schedule Final Quiz - Assignment

Schedule Final Quiz - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Before the team in Uruzgan province creates the project schedule, they agree on scheduling tools, reporting frequency, and how performance will be tracked.Which process is being executed?

Define Activities

Plan Schedule Management

Control Schedule

Planning framework setup involving tool alignment, stakeholder dashboards, and scheduling baselines

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While preparing for construction in Daykundi province, the team breaks the high-level deliverable “Build clinic” into smaller tasks such as digging, plumbing, and tiling. What process are they carrying out?

Develop Schedule

Estimate Activity Durations

Define Activities

Subtask planning with task deconstruction, effort assignment, and resource pooling

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In an effort to build logical task flow in Ghazni province, the coordinator arranges activities based on dependencies, ensuring proper task order and timing. Which process is being followed?

Develop Schedule

Estimate Activity Durations

Sequence Activities

Task logic alignment using relationship modeling and sequence buffering

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After receiving input from engineers in Laghman province, the project manager calculates that each solar panel installation will take four days based on historical data. Which process does this reflect?

Estimate Activity Durations

Define Activities

Control Schedule

Effort forecasting through resource review and benchmarked productivity metrics

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Using MS Project in Berlin, the team inputs task durations and dependencies, then analyzes the Gantt chart and critical path to set a realistic timeline. What process are they completing?

Develop Schedule

Control Schedule

Sequence Activities

Time modeling through logic-driven schedule creation with float and path visibility

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing actual progress against the plan in Balkh province, the manager notices that key activities are behind schedule and considers adding weekend work to catch up. What process is this?

Develop Schedule

Control Schedule

Define Activities

Reactive scheduling review using baseline comparison and corrective action evaluation

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kabul, a documentation task is allowed to start two days before coding is complete, to accelerate delivery without waiting for 100% task finish. Which scheduling technique is being used?

Lag

Crashing

Lead

Task concurrency model with forecast-based overlap and priority realignment