Cost Management Terms - Assignment

Cost Management Terms - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

Green Belt After Define Phase

Green Belt After Define Phase

Professional Development

10 Qs

LEEDv4 - Water Efficiency

LEEDv4 - Water Efficiency

Professional Development

10 Qs

Planning for Success Part 2

Planning for Success Part 2

Professional Development

7 Qs

Introduction to Project Management

Introduction to Project Management

Professional Development

10 Qs

SG20_Test_S3_Ch4_Integration

SG20_Test_S3_Ch4_Integration

Professional Development

10 Qs

PRE TEST

PRE TEST

Professional Development

10 Qs

MIPS

MIPS

Professional Development

9 Qs

9. Chapter 3 - Calculation (Quiz 2)

9. Chapter 3 - Calculation (Quiz 2)

Professional Development

7 Qs

Cost Management Terms - Assignment

Cost Management Terms - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Herat province, a project manager calculates how much value should have been earned based on the schedule at this point in the project timeline.Which cost term is being described?

Planned Value (PV)

Earned Value (EV)

Cost Variance (CV)

Value expectation baseline using forward-loaded financial alignment and phased milestone calibration

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing progress in Bamyan province, the manager calculates the value of the work actually completed so far, regardless of the money spent. What term is used for this measure?

Earned Value (EV)

Actual Cost (AC)

Estimate at Completion (EAC)

Delivery effectiveness index through effort-backed forecasting and deliverable-based stakeholder alignment

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Balkh province, the project accountant reports the total amount of money already spent on the project to date. Which cost metric is being used?

Actual Cost (AC)

Earned Value (EV)

Cost Performance Index (CPI)

Expense accumulation tracker tied to multi-phase budget cycles and financial effort recording

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As part of a mid-project evaluation in Kabul, the manager compares earned value to actual cost and sees that the project is over budget. What metric reveals this financial overrun?

Cost Variance (CV)

Budget at Completion (BAC)

Schedule Performance Index (SPI)

Budget deviation index integrating stakeholder burn rate and resource expenditure alignment

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Delhi, India, the sponsor asks: "Given what we’ve spent and how we’re performing, what do you now estimate the total cost will be when the project ends?" Which term best describes this forecasted figure?

Estimate at Completion (EAC)

Planned Value (PV)

Cost Baseline

Predictive forecast model based on earned value efficiency, current cost tracking, and resource allocation trends